This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- NTT Global Data Centers
- Address and locality
- Mesa · Maricopa County · Arizona
- Lifecycle status
- reported proposed
- Facility type
- data center
- Reported capacity
- Planned: 360 MW (source-reported; boundary not independently verified)
- Source freshness
- 8 August 2026
- Location precision
- exact
- Source confidence
- reported
- Stable directory ID
dcd-dir-001074
What the source record says
investmentUsd is $300M land purchase only; total buildout investment is substantially higher. NE corner of Pecos and Crismon roads, far SE Mesa. Seven two-story buildings totaling 1.7M sq ft + warehouse + office. NTT's second Phoenix-area campus (existing 102-acre, 240MW campus is ~4 miles north on Elliot Road). Phase 1 targeted November 2028. Coordinates approximate for Pecos/Crismon intersection. Status refresh 2026-08-08: the Planning & Zoning Board recommended approval 4-0 in mid-May 2026; the article (updated 2026-06-08) said the proposal "will likely be heard in late July or mid-August by council". No fetched source records a Council vote, so the status stays "proposed" — the 2026-07-20 date carried in earlier notes was an expected hearing date, not a decision.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2023-11 · reported proposed
Project first proposed as Pacific Proving Technology Park; NTT filed pre-submittal with City of Mesa
- 2026-05 · reported proposed
Mesa Planning Commission voted unanimously to recommend rezoning; council vote was pending summer 2026
- 2026-05 · reported proposed
Mesa's Planning and Zoning Board voted 4-0 to recommend that City Council approve NTT's rezoning, council use permit and major site plan modification for the 170-acre site at Pecos and Crismon roads. A recommendation only — the Council decision had not been taken.
Sources and attribution
- NTT acquires 173-acre planned data center park in Mesa for $300m · Data Center Dynamics
- Mesa residents are fighting a Tokyo tech giant's data center · Copper Courier
- Big data center in SE Mesa passes first review — Planning & Zoning Board recommends approval 4-0 for the 170-acre site at Pecos and Crismon · Mesa Tribune
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID ntt-global-mesa-az. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.