This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Address and locality
- Mesa · Maricopa County · Arizona
- Lifecycle status
- reported operational
- Facility type
- data center
- Reported capacity
- Planned: 400 MW (source-reported; boundary not independently verified)
- Source freshness
- 31 August 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000742
What the source record says
Three-phase campus through 2030; originally filed anonymously as Project Red Hawk via LLC Stone Applications. Phase 1 operational July 2025. Phase 2 under construction. Coordinates at Elliot and Sossaman roads, SE Mesa. 2019 development agreement requires >=$600M capex by 2025, >=$1B by 2029, 750,000 sq ft built by 2030, and a >=$65,000 average full-time data-center salary; construction workforce has been cited around 1,200 (an estimate, not a permanent-jobs count). Status reflects Phase 1 (Redhawk 1), operational since July 2025; Phases 2 and 3 remain under construction, which is why Google's own US locations index still lists Mesa under sites in development.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2019-01 · reported proposed
Google filed plans as 'Stone Applications LLC' for 187 acres at NW corner of Elliot and Sossaman roads
- 2025-01 · reported under construction
Phase 2 (280,000 sq ft, 185 acres) under construction targeting 2027; Phase 3 (283,500 sq ft) under Mesa Design Review Board review
- 2025-07 · reported operational
Phase 1 (288,530 sq ft data hall, Redhawk 1) went operational July 2025 for core cloud and AI services
Sources and attribution
- Google breaks ground on Mesa data center campus in Arizona · Data Center Dynamics
- Google Planning Next Phase of Mesa Data Center Facility · AZBEX
- Mesa Council approves $1bn Google data center, with $16m in tax breaks · Data Center Dynamics
- City of Mesa resolution authorising a development agreement and lease with Stone Applications, LLC for ~187 acres at S Sossaman Rd and E Elliot Rd (approved 1 July 2019)
- City of Mesa Office of Economic Development study-session presentation, 27 June 2019 — GPLET term: ~$32,967,000 excise payable over 25 years vs ~$48,916,134 ad valorem otherwise
- Executed GPLET Lease between the City of Mesa and Stone Applications, LLC (City of Mesa matter 19-0809) — states no abatement amount; net annual rent of $10,000 and an express disclaimer that GPLET benefits are not guaranteed during the term
- Executed Development Agreement with exhibits, City of Mesa and Stone Applications, LLC (matter 19-0809)
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID google-redhawk-mesa-az. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.