This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- DC BLOX
- Address and locality
- Lithia Springs · Douglas County · Georgia
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 120 MW (source-reported; boundary not independently verified)
- Source freshness
- 6 July 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000426
What the source record says
Initial 120 MW phase (Building A); site plan includes additional 80 MW Building B (delivery early 2028) and 80 MW Building C (early 2029) totaling 200+ MW. investmentUsd reflects green loan construction financing announced August 11, 2025. Located adjacent to Microsoft Douglasville campus, 2.5 miles from Google facility. Coordinates are Lithia Springs area centroid. Original DCD source URL returned HTTP 404 and was replaced with the DC BLOX official press release, which resolves and supports all claims. The $98M Douglasville abatement was granted for the campus in the Riverside West Business Park (New River Road); city/authority filings cite 25 permanent jobs (~$130k average) and up to 500 construction jobs over five years — projections, not confirmed headcounts.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-08-11 · reported proposed
$1.15 billion green loan financing announced; 120 MW campus on 100 acres in Lithia Springs adjacent to Microsoft campus
- 2025-09 · reported under construction
Phase 1 (120 MW Building A) construction underway; delivery targeted 2026
Sources and attribution
- DC BLOX Secures $1.15 Billion Green Loan for Atlanta Data Center Campus Development · DC BLOX
- Atlanta West Hyperscale Data Center Campus – DC BLOX official page · DC BLOX
- City approves $98 million tax break for expanded data site · Douglas County Sentinel
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID dc-blox-atlanta-west-ga. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.