This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- QTS Data Centers
- Address and locality
- Fairfield · Utah County · Utah
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 650 MW (source-reported; boundary not independently verified)
- Source freshness
- 15 August 2026
- Location precision
- approximate
- Source confidence
- reported
- Stable directory ID
dcd-dir-001202
What the source record says
Sweetwater Industrial Park Community Reinvestment Project Area #3 (Eagle Mountain Redevelopment Agency, Title 17C): 61% of Real Property Tax Increment plus 74% of Personal Property Tax Increment, reimbursed per Phase for 20 years per phase (not to exceed 40 years total), from Utah County, Alpine School District, Eagle Mountain City, Central Utah Water Conservancy District, and the Unified Fire Service Area. The signed CRA Participation Agreement's Participant is QTS Eagle Mountain I, LLC — there is no separate agreement naming "QTS Eagle Mountain II, LLC." This parcel (38:707:0002, 98.043 acres) is covered by the Sweetwater CRA #3 agreement with QTS Eagle Mountain I, LLC, which explicitly includes this parcel's acreage: the Agreement's own recitals and the amended Project Area's Table 1 Parcel List define the ~193-acre Project Area, and its terms, as spanning both the QTS Eagle Mountain I parcel (38:707:0001, 95.153 acres) and the QTS Eagle Mountain II parcel by acreage. A 2nd Amendment (approved August 20, 2024) changed only the payment mechanics — allowing personal-property reimbursements to be paid directly to QTS's colocation end-clients — and did not alter the 61%/74%/20yr/40yr terms.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
No status history was supplied in this edition.
Sources and attribution
- Data Center Growth in Utah and the United States — Data Summary, April 2026 (Planned Data Centers in Utah, March 2026) · Kem C. Gardner Policy Institute, University of Utah
- Eagle Mountain RDA Board packet — Sweetwater Industrial Park CRA #3 Amended Project Area Plan & Participation Agreement terms (August 1, 2023) · Eagle Mountain Redevelopment Agency via Utah Public Notice Website
- Eagle Mountain RDA Board packet — Sweetwater #3 CRA Participation Agreement Second Amendment (QTS Eagle Mountain I, LLC), August 20, 2024 · Eagle Mountain Redevelopment Agency via Utah Public Notice Website
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID qts-eagle-mountain-ii-fairfield-ut. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.