This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Address and locality
- The Dalles · Wasco County · Oregon
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Not stated
- Source freshness
- 10 September 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000750
What the source record says
Public-reception check (2026-09-10): Checked the Construction Dive article (2026-09-10) about this $600M, 290,000 sq ft facility (Whiting-Turner as general contractor); it covers only project economics and site-selection rationale ('energy infrastructure, developable land and available workforce'). No community reaction, hearing, or official statement documented in this source -- despite The Dalles being a site with an extensively documented history of Google water-use controversy in past years, none of that appears in this particular article, so it is not reflected here.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
No status history was supplied in this edition.
Sources and attribution
- Google taps Whiting-Turner to build $600M Oregon data center — 'Design LLC, a wholly-owned subsidiary of tech giant Google, selected Baltimore-based Whiting-Turner Contracting Co. to build a $600 million data center in Wasco County, Oregon'; 290,000 square feet; contractor cleared to start construction per The Dalles Community Development Department filings dated Jan. 30, 2024 · Construction Dive
- Google makes move to break ground on new data center in The Dalles — site is 3500 River Road at the Port of The Dalles, a former aluminum smelter site; 290,000 sq ft; up to $600 million; described as 'the fourth such data center for Google in The Dalles' · Columbia Community Connection
- As Google's water demands grow, The Dalles aims to pull more from Mount Hood forest — 'By 2024, a third of The Dalles' water went to Google's three local data center sites'; Google 'just built a data center building in 2025, and plans to complete another one this year'; Google employs about 200 people in The Dalles · Oregon Public Broadcasting
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID google-the-dalles-port-river-road-or. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.