This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- DC BLOX
- Address and locality
- Warren Township · Marion County · Indiana
- Lifecycle status
- reported permitted
- Facility type
- data center
- Reported capacity
- Planned: 78 MW (source-reported; boundary not independently verified)
- Source freshness
- 13 September 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000434
What the source record says
Three-building campus, scaled back from an original 28MW-larger plan. Capex breakout: $700-800M construction + $1.3-1.4B in 'servers, networking equipment, and AI hardware' per the developer's own figures. Coordinates are approximate.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-07-20 · reported permitted
Indianapolis Metropolitan Development Commission voted 6-1 on 2026-07-15 to approve DC BLOX's scaled-back data center campus at the Thunderbird Commerce Center in Warren Township — the final local approval (rezoning/variance) needed to proceed. Advances the record from proposed to permitted.
Sources and attribution
- DC Blox data center in eastern Indianapolis receives recommendation for approval · Data Center Dynamics
- East side data center wins approval, despite community opposition · WFYI
- DC Blox data center gets key approval despite community opposition · WRTV
- HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD
- Indianapolis Data Center in Marion County, Indianapolis — DC BLOX · DC BLOX
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID dc-blox-warren-township-marion-county-in. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.