North Creek Technology Campus (NCTC)

reported proposed

Amazon Web Services

Louisa · Louisa County · Virginia

Planned 3,000 MWSource updated 10 September 2026approximate location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Amazon Web Services
Address and locality
Louisa · Louisa County · Virginia
Lifecycle status
reported proposed
Facility type
data center
Reported capacity
Planned: 3,000 MW (source-reported; boundary not independently verified)
Source freshness
10 September 2026
Location precision
approximate
Source confidence
reported
Stable directory ID
dcd-dir-000152

What the source record says

Preliminary estimate of at least 17 total DC buildings across both Louisa campuses combined; ~628 of the 1,444-acre assemblage held as open space, ~380 acres to be donated to the county for a public park. No formal local rezoning/SUP filing yet as of the cited meeting — status set to 'permitted' cautiously based on land-disturbance-adjacent county process; confirm before elevating capacity figures (3GW is a stated potential ceiling from 10 substations, not a committed buildout). Status corrected to proposed: no formal permit or site plan filed as of the Nov 2024 Planning Commission buffer/landscaping discussion (still exploratory). 'Up to 3 GW' = ten 300 MW substations (a ceiling, not permitted capacity). Public-reception check (2026-09-10): North Creek Technology Campus (NCTC) is confirmed distinct from a THIRD AWS Louisa County proposal (near Northeast Creek Reservoir/Mineral) that Amazon withdrew 2025-07-25/28 after strong resident opposition ("Please don't Loudoun Louisa... Please say no to this additional data center," per a July 2025 board-of-supervisors public-comment session). NCTC itself was one of two AWS campuses approved by-right under the county's Technology Overlay District and moved to construction without the surge of documented opposition seen on the third project. No hearing/vote record specific to NCTC was found. Checked: Virginia Business, a Louisa data-center timeline site, and a local Substack covering county supervisors' meetings.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2024-11-09 · reported proposed

    proposed per Louisa County Planning Commission buffer/landscaping plan discussion (Nov. 9, 2024) + county-sourced reporting

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID aws-north-creek-technology-campus-louisa-va. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →