This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Amazon Web Services
- Address and locality
- Bristow · Prince William County · Virginia
- Lifecycle status
- reported permitted
- Facility type
- data center
- Reported capacity
- Not stated
- Source freshness
- 6 July 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000063
What the source record says
$700M land purchase is among the highest ever for undeveloped land in the US. Zoning allows up to 3.5 million sq ft of data center space and three substations. Adjacent to Microsoft's Bristow campus parcel. Coordinates approximate for northwest corner of Devlin and Linton Hall roads.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2022-01 · reported proposed
Stanley Martin Homes assembled 270-acre site and applied for rezoning for up to 3.5 million sq ft of data center use
- 2023-11 · reported permitted
County Board approved rezoning; circuit court upheld 2024; Virginia Court of Appeals upheld September 2025. Amazon purchased 188.5 acres (70% of park) from Stanley Martin for $700M on November 5, 2025.
Sources and attribution
- Amazon buys 189 acres in Prince William tech park for $700M · Virginia Business
- Amazon pays $700M for planned data center site in Virginia's Prince William County · Data Center Dynamics