Amazon AWS Gilroy Data Center

reported under construction

Amazon Web Services

8050 Camino Arroyo · Gilroy · Santa Clara County · California · 95020

Planned 98 MWSource updated 14 September 2026exact location · confirmed source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Amazon Web Services
Address and locality
8050 Camino Arroyo · Gilroy · Santa Clara County · California · 95020
Lifecycle status
reported under construction
Facility type
data center
Reported capacity
Planned: 98 MW (source-reported; boundary not independently verified)
Source freshness
14 September 2026
Location precision
exact
Source confidence
confirmed
Stable directory ID
dcd-dir-000064

What the source record says

Status updated to under_construction: grading permit issued December 11, 2025; building permit issued March 19, 2026; City of Gilroy lists project as Under Construction as of July 2026. Site at 8050 Camino Arroyo in east Gilroy along Hwy 101. Full build-out: 438,000 sq ft across 56 acres. Amazon cites a ~$2 billion investment for the Gilroy project (recorded as investmentUsd); its broader Northern California investment of ~$5.1B and ~1,890 jobs since 2009 is regional and not attributable to this site. The 2020 land purchase was $31.3M. Operational job figures conflict and are unconfirmed: the FEIR says employment 'may grow to 50 full-time employees' (a ceiling), the permit application lists 25, and Amazon's promotional materials cite ~90 on-site; the construction workforce is not disclosed.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2020-11 · reported proposed

    Permit application initially received by City of Gilroy; Amazon purchased 56-acre site for $31.3M in 2020

    Open cited source →

  2. 2025-07 · reported permitted

    Gilroy Community Development Director Sharon Goei approved Phase 1 (218,000 sq ft building, 49MW PG&E connection) on July 3, 2025; appeal filed July 21, 2025, withdrawn August 18, 2025

    Open cited source →

  3. 2026-03 · reported under construction

    Grading permit issued December 11, 2025; building permit issued March 19, 2026; City of Gilroy project listing shows status as Under Construction

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID amazon-gilroy-ca. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →