Aligned Data Centers — Pataskala

reported cancelled

Aligned Data Centers

Pataskala · Licking County · Ohio

Planned 200 MWSource updated 2 September 2026approximate location · confirmed source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Aligned Data Centers
Address and locality
Pataskala · Licking County · Ohio
Lifecycle status
reported cancelled
Facility type
data center
Reported capacity
Planned: 200 MW (source-reported; boundary not independently verified)
Source freshness
2 September 2026
Location precision
approximate
Source confidence
confirmed
Stable directory ID
dcd-dir-000045

What the source record says

Blocked 200 MW campus (89 acres, 3 planned buildings, down from 4) at Broad St & Mink St in the Pataskala industrial park, which would have run on on-site Bloom Energy natural-gas fuel cells. The Planning & Zoning Commission voted 5–2 on 2026-06-03 to recommend rejection (staff had recommended approval), and City Council rejected the site plan 7-0 on 2026-08-25. Recorded as cancelled because the city denied the application; note that Aligned itself has not abandoned the project — its general counsel said the company would “reflect and regroup.” A citizen charter amendment banning data centers over 25 MW goes to Pataskala and Granville voters on Nov. 3, 2026. Coordinates approximate (Pataskala city-center).

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-08-25 · reported cancelled

    Pataskala City Council voted 7-0 on Aug. 25, 2026 to reject the site plan, accepting the Planning and Zoning Commission's recommendation to deny it. Aligned has not withdrawn — its general counsel said only that the company would “reflect and regroup.” A separate citizen charter amendment banning data centers over 25 MW goes to Pataskala and Granville voters on Nov. 3, 2026.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID aligned-pataskala-licking-oh. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →