Microsoft Tyrone Campus (Project Rita)

reported permitted

Microsoft

Tyrone · Fayette County · Georgia

Planned 96 MWSource updated 7 July 2026exact location · confirmed source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Microsoft
Address and locality
Tyrone · Fayette County · Georgia
Lifecycle status
reported permitted
Facility type
data center
Reported capacity
Planned: 96 MW (source-reported; boundary not independently verified)
Source freshness
7 July 2026
Location precision
exact
Source confidence
confirmed
Stable directory ID
dcd-dir-001006

What the source record says

Two-building campus (two 48 MW buildings = 96 MW, ~490,000-500,000 sq ft) plus an on-site substation; codename Project Rita. Part of Microsoft's East US 3 Azure region (planned 2027). Total site ~161 acres (~146.4 in Tyrone + ~14.5 in Fairburn). As of June 2 2026 no site plan or building permits filed. Microsoft requested no tax abatements (none offered). No investment figure disclosed. Coordinates approximate (address-derived; 2044 GA-74). Estimated ~4,000 gallons/day operational water use.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2023-11 · reported proposed

    DRI (Development of Regional Impact) application filed; project first surfaced publicly

    Open cited source →

  2. 2024-03-28 · reported permitted

    Rezoning approved by Tyrone Town Council

    Open cited source →

  3. 2026-05-05 · reported permitted

    Microsoft publicly confirmed the project via Microsoft Local blog; no site plan or building permits filed as of June 2 2026

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID microsoft-tyrone-ga. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →