Microsoft Malaga Campus

reported under construction

Microsoft

Malaga Alcoa Highway · Malaga · Chelan County · Washington

Planned 288 MWSource updated 5 September 2026exact location · confirmed source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Microsoft
Address and locality
Malaga Alcoa Highway · Malaga · Chelan County · Washington
Lifecycle status
reported under construction
Facility type
data center
Reported capacity
Planned: 288 MW (source-reported; boundary not independently verified)
Source freshness
5 September 2026
Location precision
exact
Source confidence
confirmed
Stable directory ID
dcd-dir-000990

What the source record says

Three-building campus at 5375 Malaga Alcoa Highway; two additional buildings possible by 2027 on demand. 288 MW figure from secondary aggregator Cleanview only; primary sources (DCD, Microsoft) do not specify MW capacity. Construction of first building began June 2023 per Microsoft Local blog; original statusHistory incorrectly dated under_construction to 2024-05. Expected operational 2026. Coordinates approximate for Malaga area on Malaga Alcoa Highway. A Building-1 permit cites ~72 peak-shift staff (a single-building figure, not a facility employment total); no confirmed total campus capital-expenditure figure is public. Go-live check 2026-08-08: NO citable operational date exists. Microsoft's own Malaga project page gives a first-phase construction window concluding in early 2026 but states plainly that "Completion of construction does not indicate datacenter operation/availability", and publishes no energization or service date. Secondary reporting that the first building would be "powered in August and fully operational by late 2026" is forward-looking and was not used to move the status. Remains under_construction. Microsoft's own Quincy/Central Washington community page states it "operates datacenters in Quincy and is developing new datacenters in Malaga and East Wenatchee" — positively confirming the site is not yet operational.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2022-04 · reported proposed

    Microsoft acquired 102.5 acres on Malaga Alcoa Highway for $9.2M across three parcels

    Open cited source →

  2. 2023-03 · reported permitted

    Permits filed for three data center buildings on Malaga Alcoa Highway; Chelan County

    Open cited source →

  3. 2023-06 · reported under construction

    Construction of first datacenter building commenced June 2023 per Microsoft Local blog; Jumpoff Ridge Substation also under construction on campus

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID microsoft-malaga-wa. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →