Facility snapshot
- Operator as published
- Microsoft
- Address and locality
- Heath · Licking County · Ohio
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Not stated
- Source freshness
- 6 July 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000981
What the source record says
Site at 975 Thornwood Dr SW, Heath OH 43056; 227 acres. Part of Microsoft's $1B Licking County three-campus investment alongside Hebron and New Albany. Coordinates are approximate Heath city centroid; exact Thornwood Dr parcel not pinned. The $1B is Microsoft's three-campus Licking County commitment; no Heath-specific capital-investment figure is published (do not derive by subtraction).
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2024-10 · reported proposed
Announced as part of $1B Licking County investment; Microsoft purchases 227 acres at 975 Thornwood Dr SW, Heath for over $32M
- 2025-04 · reported proposed
Microsoft pauses all Licking County sites
- 2026-02 · reported under construction
Groundbreaking February 24, 2026; AMES Construction as general contractor; mass grading began February, targeted complete November 2026
Sources and attribution
- Heath datacenter construction updates - Microsoft Local · Microsoft Local
- Heath breaks ground on Microsoft data center expected to bring hundreds of jobs · ABC 6 WSYX Columbus
- Ohio data centers exploit tax break · Signal Ohio
- Understanding Microsoft datacenters in Licking County · Microsoft Local
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID microsoft-heath-oh. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This exact source identifier is linked to Microsoft — Heath campus. The licensed row remains a separate discovery record.