Licensed lead · not independently verified · dcd-dir-000978

Microsoft Project Ginger West Data Center

reported under construction

Microsoft

11100 Booneville Road · West Des Moines · Polk County · Iowa

Capacity not statedSource updated 16 September 2026exact location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Microsoft
Address and locality
11100 Booneville Road · West Des Moines · Polk County · Iowa
Lifecycle status
reported under construction
Facility type
data center
Reported capacity
Not stated
Source freshness
16 September 2026
Location precision
exact
Source confidence
reported
Stable directory ID
dcd-dir-000978

What the source record says

Site at 11100 Booneville Rd area, West Des Moines (Polk County). 1.8M sq ft planned across multiple buildings. Turner Construction is general contractor; completion estimated summer 2028. Companion Ginger East campus (124 acres, 5 buildings) is a separate site in West Des Moines. Part of Microsoft's multi-billion dollar total Iowa investment since 2009. Planned MW capacity not confirmed from primary sources; 444 MW figure removed as unsupported. Iowa's Sec. 423.3(95) data-center sales-tax exemption applies, but Iowa data-center incentive awards are not publicly disclosed; no Ginger West-specific job count is published.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2021 · reported proposed

    West Des Moines approved first two buildings of Ginger West; construction start targeted September 2021

    Open cited source →

  2. 2021 · reported under construction

    Construction underway; first building came online 2023 (244,676 sq ft); additional phases ongoing targeting summer 2028 completion

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID microsoft-ginger-west-ia. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →