This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Lambda
- Address and locality
- Kansas City · Platte County · Missouri
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 100 MW (source-reported; boundary not independently verified)
- Source freshness
- 26 July 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000855
What the source record says
11155 N. Airworld Dr (former Bank of America campus, ~16.9 acres), Platte County near KCI airport. Launches early 2026 with 24 MW confirmed; >100 MW is a scale-up ceiling (planned figure). Distinct parcels from Google (Project Mica) and Meta's Kansas City sites. Eligible for the Missouri Data Center Sales Tax Exemption (eligibility only — no award amount confirmed; honest-zero). The >$500M figure is a press estimate (notes). Dedicated to a single unnamed AI customer under a multi-year agreement.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025 · reported under construction
Lambda to build an AI factory at 11155 N. Airworld Dr (former Bank of America campus); launching early 2026 with 24 MW, scaling toward 100+ MW
Sources and attribution
- AI cloud firm Lambda targets data center deployment in Kansas City, Missouri · Data Center Dynamics
- Lambda to build a 100MW AI factory in Kansas City, MO · Lambda
- Missouri Department of Economic Development — press release
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID lambda-kansas-city-mo. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.