Facility snapshot
- Operator as published
- Iron Mountain
- Address and locality
- Boyers · Butler County · Pennsylvania
- Lifecycle status
- reported operational
- Facility type
- data center
- Reported capacity
- Planned: 40 MW (source-reported; boundary not independently verified)
- Source freshness
- 31 August 2026
- Location precision
- approximate
- Source confidence
- reported
- Stable directory ID
dcd-dir-000829
What the source record says
333,000 sq ft of data center space 220 feet underground in a former limestone mine on a 200-acre campus, about an hour north of Pittsburgh. Operator states 40 MW of total potential capacity; the currently energised load is not published, so the figure is recorded as planned rather than operational. Long-standing colocation/records site rather than an AI buildout — no aiClassification asserted.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
No status history was supplied in this edition.
Sources and attribution
- Iron Mountain — Western Pennsylvania Data Center (WPA-1) · Iron Mountain
- Data Centers in Pennsylvania — Project List & Locations (Iron Mountain WPA-1, Butler County) · Cleanview
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID iron-mountain-wpa-1-boyers-butler-county-pa. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.