Crusoe Warrenton Campus

reported permitted

Crusoe

Warrenton · Warren County · Missouri

Capacity not statedSource updated 7 July 2026exact location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Crusoe
Address and locality
Warrenton · Warren County · Missouri
Lifecycle status
reported permitted
Facility type
data center
Reported capacity
Not stated
Source freshness
7 July 2026
Location precision
exact
Source confidence
reported
Stable directory ID
dcd-dir-000351

What the source record says

Coordinates approximate. Site address: 22151 NW Service Road, Warrenton MO; north of NW Service Road, west of Hwy. W. Two 805,000 sq ft data center buildings + 40,000 sq ft administration building + 621,250 sq ft Ameren-owned switch yard + 603,200 sq ft Crusoe-owned electrical substation. Crusoe described as its 'fifth campus' in its national AI data center portfolio as of June 2026 per Crusoe newsroom. Meta signed agreement with Crusoe in June 2026 for approximately 1.6GW of AI computing capacity split across Childress TX and Warrenton MO campuses — per-site split not disclosed; confirms Warrenton as AI anchor customer site (sourceRef 3). Status: conditional use permit and site plan approved; land disturbance review and construction permits still outstanding before groundbreaking. Crusoe committed publicly to seek no real property tax or gross receipt tax abatements; would pursue state incentives only (sourceRef 2). Developer projected annual property taxes ~$80M/year (sourceRef 1), with ~$44M to local schools. Construction jobs projected ~2,000-2,500 over ~3-year build; permanent tech jobs projected ~100 (developer estimates, sourceRef 1 and 2 — not firm contractual commitments). Crusoe historically used on-site flared natural gas but divested those operations; Warrenton campus is grid-connected via Ameren Missouri — no on-site gas generation reported here. Distinct from the Google/Crusoe 'Goodnight' campus in Armstrong County TX.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025 · reported proposed

    Crusoe named as developer at Warrenton Board of Aldermen meeting on November 4, 2025; announcement made by Greater Warren County Economic Development Council consultant.

    Open cited source →

  2. 2026 · reported permitted

    Warrenton Planning & Zoning Commission approved conditional use permit and site plan 8-2 on January 8, 2026; Board of Aldermen approved unanimously (two 6-0 votes) on January 20, 2026. Still requires land disturbance review and construction permits before groundbreaking.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID crusoe-warrenton-mo. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.