Facility snapshot
- Operator as published
- Cologix
- Address and locality
- Johnstown · Licking County · Ohio
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 800 MW (source-reported; boundary not independently verified)
- Source freshness
- 26 July 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000292
What the source record says
154 acres; up to 800 MW scalable across eight data centers / 2.0M sq ft (800 MW is a full-buildout potential — in notes). The '>$7 billion' figure is a company-wide expansion plan, not a Johnstown-specific committed amount (in notes). Coordinates are the Johnstown, Licking County area centroid. The '>$7B' figure is Cologix's company-wide expansion plan; the $1.17B commitment is combined across Johnstown + Orange Township (not split) -> investmentUsd omitted. Land: ~$45M for 154 acres (Sept 2024).
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025 · reported under construction
Cologix acquired 154 acres in Johnstown for an 8-building AI-ready campus; first-phase development anticipated to begin 2025
Sources and attribution
- Cologix Expands Central Ohio Footprint with Land Acquisition for New AI-Ready 800MW Data Center Campus · Cologix
- Ohio approves last data-center exemption before moratorium · Signal Ohio
- Cologix expands in Central Ohio · Columbus Region
- Cologix plans 800-MW data center complex in Ohio · POWER Magazine