Record details
- Record ID: kingston-technology-hub-bartow-ga
- Record type: project
- Developer: Thor Acquisition WC LLC
- Operator: Not named in the cited records
- Owner: Robert C. Cha, Silvana U. Cha, Christine Cha Choe, and Christopher H. Choe
- Tenant: Not named in the cited records
- Capacity: Unknown (No independently supported figure)
- Location: Kingston, GA
- County: Bartow County
- Location precision: unknown — The initial DRI form lists Kingston as the submitting local government and Bartow County tax parcel 0037-0197-001 as the location.
How to read developer, owner, operator and tenant →
How to read power and capacity figures →
What remains unknown
- critical IT capacity
- utility service capacity
- operator
- tenant
- current construction status on the ground
- whether Kingston grants the rezoning
- relationship, if any, between Thor Acquisition WC LLC and Thor Equities
Sources
-
Georgia Department of Community Affairs (DCA) →Gov. record
Exact location Submissions table row DRI #4835: Kingston Technology Hub; Bartow County; Kingston; development type and process status; no operator column
What it supports Statewide DRI index row for this project only. It does not name an operator.
-
Georgia Department of Community Affairs (DCA) →Gov. record
Exact location Initial DRI Information Form, DRI #4835: Submitting Local Government Kingston; Project Kingston Technology Hub; Description One (1) Approximately 350,000 Square Foot Proposed Data Center Facility in Bartow County, GA; Developer Thor Acquisition WC LLC; action requested Rezoning
What it supports Local-government-filed initial DRI form naming the project, developer and owners and requesting rezoning. Stated building area and acreage are separate figures, not a derived campus size.
-
Georgia Department of Community Affairs (DCA) →Gov. record
Exact location DRI Application Summary #4835: Kingston Technology Hub; Jurisdiction Kingston; Developer Thor Acquisition WC LLC; DRI Status Certified Complete
What it supports State DRI review-status record. Certified Complete is regional-review completeness, not rezoning approval or operation.
Record history
Record history · 4 September 2026 · DataCenterData review
kingston-technology-hub-bartow-ga → Record
Why An initial DRI form was filed for the Kingston Technology Hub rezoning proposal.
Evidence No additional evidence link; see the linked record or claim.
New record · 18 September 2026 · DataCenterData review
kingston-technology-hub-bartow-ga → Publication
Why Added from the opened Georgia DRI filing after operator-null review; Thor Equities is not stated as a parent in the cited records.
Evidence No additional evidence link; see the linked record or claim.
Data + actions
Suggest a correction → Include record ID kingston-technology-hub-bartow-ga, the field, and a supporting primary source. Accepted corrections appear on Changes.