Record details
- Record ID: goodman-energy-park-data-center-vernon-ca
- Record type: campus
- Developer: Not named in the cited records
- Operator: Not named in the cited records
- Owner: Owner of record not established
- Tenant: Not named in the cited records
- Capacity: up to 99 MW (onsite generation planned · campus scope)
- Capacity boundary: Proposed emergency backup generation only. The CEC page states the facility would be used exclusively to provide up to 99 MW of backup emergency generation when Vernon Public Utility electricity is unavailable. This is not IT load, utility service capacity, or permitted generation. Do not aggregate it with other figures.
- Location: Vernon, CA
- County: Los Angeles County
- Location precision: approximate — CEQAnet and the CEC page place two data-center buildings at 3163 and 3049 East Vernon Avenue, Vernon, on parcels 6303-005-035 and 6303-005-036.
- Physical scale: Two data-center buildings at 3163 and 3049 East Vernon Avenue, as stated in the CEC and CEQAnet notices.
How to read developer, owner, operator and tenant →
How to read power and capacity figures →
What remains unknown
- critical IT capacity
- utility service capacity or requested load from Vernon Public Utility
- developer
- operator
- tenant
- owner of the data-center buildings as distinct from the backup-generating-facility docket applicant
- whether the City of Vernon has granted any land-use entitlement
- whether the CEC has granted or denied the Small Power Plant Exemption
- building floor areas
- construction start or completion dates
Sources
-
Governor's Office of Land Use and Climate Innovation (LCI) / State Clearinghouse CEQAnet →Gov. record
Exact location SCH 2026080118, NOP document page 'Vernon Backup Generating Facility'; Summary rows SCH Number / Lead Agency / Document Type / Received; Document Description; Contact Information; Location Parcel Number; Total Acres; Notice of Completion review-period rows
What it supports CEQAnet listing for the California Energy Commission Notice of Preparation of a Draft EIR, received by the State Clearinghouse 8/5/2026. Lead Agency: California Energy Commission. Document Description states that GIC Vernon LLC is applying to the CEC for a Small Power Plant Exemption for the Vernon Backup Generating Facility, a 99 MW emergency only power system that will support the Goodman Energy Park (GEP) data center in the City of Vernon; that the GEP consists of two data center buildings near Vernon Avenue and Soto Street at 3163 and 3049 East Vernon Avenue; forty (40) diesel generators, thirty eight (38) at 3 MW for data center critical loads and two 1 MW house generators; designed to operate only when electricity from Vernon Public Utility is unavailable; will not connect to the regional transmission grid or export power. Location rows give Cities 'Vernon', Counties 'Los Angeles', Cross Streets 'Vernon Avenue and Soto Street', Zip 90058, Total Acres 11.55, Parcel # 6303-005-035 and 6303-005-036, Coordinates 34°0'24.89"N 118°13'4.68"W. Contact Information names Ward Mace, Agency Name GIC Vernon LLC, Job Title Regional Director, Contact Types 'Project Applicant'.
-
Vernon Backup Generating Facility (VBGF) - California Energy Commission project page →Gov. record
Exact location Summary table rows 'Project Owner', 'Docket Number', 'Capacity', 'Location', 'Technology', 'Project Status', 'Project Type'; 'Project Description' paragraphs 1-2; 'Data Centers' section; 'Small Power Plant Exemption' section
What it supports California Energy Commission project page for docket 25-SPPE-01. Summary table: Project Owner 'GIC Vernon LLC'; Capacity '99 MW'; Location 'Vernon, California'; Technology 'Backup Generating System'; Project Status 'Under Review'; Project Type 'Small Power Plant Exemption'. Project Description states the VBGF would consist of forty (40) diesel fired generators used exclusively to provide up to 99 megawatts (MW) of backup emergency generation to support the Goodman Energy Park Data Center (GEP) when electricity from Vernon Public Utility (VPU) is unavailable; that the GEP would consist of two data center buildings, Building 1 at 3163 East Vernon Avenue and Building 2 at 3049 East Vernon Avenue; that the VBGF would not be electrically interconnected to the transmission grid; that VPU would own and operate a new switching station on the GEP site; and that the project applicant GIC Vernon would own and operate the Project Substation. The page states the CEC does not permit data centers, and that in granting an SPPE the CEC is not the final approval necessary for construction and operation of a project.
Record history
Record history · 5 August 2026 · DataCenterData review
goodman-energy-park-data-center-vernon-ca → Record
Why The State Clearinghouse received the CEC Notice of Preparation of a Draft EIR (SCH 2026080118). Received is not a publication or approval date.
Evidence No additional evidence link; see the linked record or claim.
New record · 18 September 2026 · DataCenterData review
goodman-energy-park-data-center-vernon-ca → Publication
Why Added from the opened CEQAnet and CEC records. Backup-generation capacity is recorded as proposed onsite generation, not IT load.
Evidence No additional evidence link; see the linked record or claim.