This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Prime Data Centers
- Address and locality
- Avondale · Maricopa County · Arizona
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 240 MW (source-reported; boundary not independently verified)
- Source freshness
- 10 September 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001145
What the source record says
5-building, 66.5-acre campus; groundbreaking on first 3 buildings May 2026.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-05 · reported under construction
Groundbreaking on first 3 buildings.
Sources and attribution
- Prime Data Centers breaks ground on three buildings at its 240MW Phoenix campus, advancing $3 billion investment in Avondale · Prime Data Centers
- Prime Data Centers PHX01 tech sheet — spec table: 'UTILITY PROVIDER SRP', 'ACRES 66.5', 'CRITICAL IT LOAD 240MW'; 'a closed-loop cooling system engineered for zero process water use during operations'
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID prime-avondale-az. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.