This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Meta
- Address and locality
- Near East 11th Street & 193rd East Avenue (Fair Oaks industrial park, East Tulsa) · Tulsa · Tulsa County · Oklahoma
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Not stated
- Source freshness
- 6 August 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000926
What the source record says
Codename: Project Anthem (used in TMAPC filings; Meta confirmed publicly April 21, 2026). Meta's 28th US data center and 32nd globally; first in Oklahoma and first built within Tulsa city limits. Anchor tenant at Fair Oaks Innovation Park (a 2,000-acre campus) near 11th Street and Creek Turnpike, East Tulsa. Investment stated as 'more than $1 billion' by Meta — a floor figure only; PartnerTulsa estimates construction costs at ~$800M. investmentUsd omitted: no firm single confirmed figure. Facility size: 2+ million sq ft; completion targeted 2028; general contractor Fortis Construction. No facility-specific MW capacity disclosed; Meta separately adding 1,500+ MW of clean energy to the Oklahoma grid statewide. Jobs: Meta states 'more than 1,000 construction workers at peak' and 'approximately 100 permanent jobs' — approximations from press release, not firm figures; omitted from numeric fields. Phase 2 expansion (375 additional acres west of original parcel, developer Atmoss LLC) proposed but withdrawn March 2026 before city council vote. Coordinates approximate (near 11th St & Creek Turnpike, East Tulsa).
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2024 · reported proposed
Preliminary plat filed with Tulsa Metropolitan Area Planning Commission as 'Project Anthem'; Meta identity not publicly confirmed at time of filing
- 2024 · reported permitted
Preliminary plat approved August 7, 2024 by TMAPC; developer entity listed as Atmoss LLC
- 2026 · reported under construction
Meta publicly confirmed as operator; groundbreaking ceremony held April 21, 2026 with Oklahoma Governor Kevin Stitt; completion targeted 2028
Sources and attribution
- Breaking Ground on a New AI-Optimized Data Center in Tulsa, Oklahoma · Meta (about.fb.com)
- Hello, Tulsa! — Meta Data Centers · Meta (atmeta.com)
- Meta Breaks Ground on New $1 Billion Data Center in Tulsa · Oklahoma Department of Commerce
- Meta's east Tulsa data center earns praise and protests · Tulsa Flyer
- 340-acre data center campus planned in Tulsa, Oklahoma · Data Center Dynamics
- Gov. Stitt announces Meta behind Tulsa data center known as 'Project Anthem' · NewsOn6
- Meta confirmed as company behind Project Anthem · FOX23 News
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID meta-anthem-tulsa-ok. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.