Bitdeer Knoxville AI Datacenter (5101 S. National Drive)

reported under construction

Bitdeer

Knoxville · Knox County · Tennessee

Planned 86 MWSource updated 9 September 2026approximate location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Bitdeer
Address and locality
Knoxville · Knox County · Tennessee
Lifecycle status
reported under construction
Facility type
data center
Reported capacity
Planned: 86 MW (source-reported; boundary not independently verified)
Source freshness
9 September 2026
Location precision
approximate
Source confidence
reported
Stable directory ID
dcd-dir-000190

What the source record says

Existing Bitmain/Bitdeer Bitcoin mining site operational since May 2020 (property acquired 2018 via Commercial Purchase and Sale Agreement with Kemet Foil Manufacturing LLC, 9.88 acres / 77,678 sq ft industrial building). The 20-F discloses an active conversion to AI cloud use: Phase 1 (37MW) targeted Q4 2026, Phase 2 (49MW) targeted Q1 2027, against 86MW total electrical capacity in use as of 2026-03-31. Coordinates are an approximate parcel-area estimate for the South National Drive industrial corridor in Knox County (near APN 110-02627 per public tax-assessment/LoopNet listing) since no geocoder was available in-session to pin the exact parcel centroid — flagging for a follow-up precision pass if the site is approved. Crypto-mining site converting to AI (Bitdeer 20-F): Phase 1 37 MW targeted Q4 2026, Phase 2 49 MW Q1 2027; zero AI capacity live today (the existing 86 MW is legacy mining load being phased out). Status re-checked 2026-09-09: no change. Bitdeer's own filing still describes the Knoxville AI conversion as in design/build with a Q4 2026 target, so the record stays under_construction.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-04-30 · reported under construction

    under construction per Bitdeer Technologies Group FY2025 Form 20-F, filed 2026-04-30

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID bitdeer-knoxville-tn. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →