AVAIO Digital Perseus

reported permitted

AVAIO Digital Partners

2232 Golf Club Rd · Pittsburg · Contra Costa County · California

Planned 99 MWSource updated 14 September 2026approximate location · confirmed source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
AVAIO Digital Partners
Address and locality
2232 Golf Club Rd · Pittsburg · Contra Costa County · California
Lifecycle status
reported permitted
Facility type
data center
Reported capacity
Planned: 99 MW (source-reported; boundary not independently verified)
Source freshness
14 September 2026
Location precision
approximate
Source confidence
confirmed
Stable directory ID
dcd-dir-000114

What the source record says

Redevelopment of the former Delta View Golf Course (76 acres) into a 3-phase Pittsburg Technology Park; Phase 1 is the ~300,000 sq ft Perseus Data Center, targeting first occupancy in 2027. Status corrected to 'permitted' (not 'proposed'): the project holds a CEC opt-in certification (99 MW, Dec 8 2025) and a City of Pittsburg Commercial Design Review approval (Dec 11 2025, modified Feb 12 2026); no source confirms groundbreaking/construction has started. capacityMw.planned=99 reflects the CEC-certified figure, superseding an earlier ~92MW target; the Specific Plan's long-term ceiling of up to 500MW across the full technology park is undated/speculative and not recorded here. Investment ($800M+) is AVAIO's own Dec 2024 disclosure, widely syndicated but not independently audited. Jobs figures are not disclosed anywhere found and are omitted. aiClassification set to 'likely': AVAIO's own materials use explicit 'AI and cloud-driven deployments' language but do not publish GPU/HPC-specific technical specs. The Center for Biological Diversity's CEQA lawsuit (Case No. N24-2162, filed Dec 2024) was SETTLED in Dec 2025 (CBD agreed not to oppose Phase 1 in exchange for 100% renewable/carbon-free electricity, rooftop solar, 100% recycled water for cooling, wildlife monitoring, and a $750,000 community climate-resiliency payment) - it is not an active legal threat, though broader public opposition continues (see community).

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2024-11 · reported proposed

    Pittsburg City Council approved the Pittsburg Technology Park Specific Plan 5-0, enabling redevelopment of the former Delta View Golf Course into a 3-phase technology park including the Perseus Data Center.

  2. 2025-12-08 · reported permitted

    California Energy Commission granted opt-in certification for 99 MW (Phase 1); City of Pittsburg Zoning Administrator granted Commercial Design Review approval Dec 11, 2025, with a further modification approved Feb 12, 2026.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID avaio-perseus-pittsburg-ca. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.