Power / developer claim · OH · vantage-oh2-millersport
Company claim
Said by Vantage (company) in Vantage Millersport campus FAQ.
Checked 12 September 2026
The natural-gas power facility described as adjacent to Vantage's planned Millersport campus means the campus will not affect electricity costs for local residents or businesses.
What the evidence supports
Vantage says the proposed roughly 1,300 MW Fairfield Energy Center would power its adjacent campus without connecting to the local or regional grid. Fairfield Energy says it applied to the Ohio Power Siting Board as Case No. 26-0160-EL-BGN for up to 1,350 MW net gas generation and about 1,040 MW of battery storage, and that construction cannot begin until required approvals and permits are obtained. Those generation figures are not data-center IT capacity. The plans make the relationship clearer, but they still cannot establish future retail-bill effects as an observed outcome, and no post-hearing OPSB order is published.
Still unknown
None recorded
Evidence details
-
Vantage Millersport campus FAQ → Institution
Exact location https://vantagemillersportcampus.com/faq/
What it supports Company prediction that the campus will not affect local electricity costs. Not an observed or regulatory finding.
-
Fairfield Energy Center major-utility-facility page (OPSB case 26-0160-EL-BGN) → Institution
Exact location https://fairfieldenergycenter.com/home/utility-facility
What it supports Developer-reported pending OPSB application. Generation and storage figures are not data-center IT capacity and are not a certificate or construction authorization.
Counterevidence
None recorded.
Next check
None recorded
History
None recorded.