This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Takanock, LLC
- Address and locality
- Strasburg · Shenandoah County · Virginia
- Lifecycle status
- reported proposed
- Facility type
- data center
- Reported capacity
- Planned: 180 MW (source-reported; boundary not independently verified)
- Source freshness
- 9 September 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001425
What the source record says
87-acre site on Borden Mowery Drive near Interstate 81 Exit 296 and the Mercury Paper plant in Strasburg's industrial park; roughly 2 million sq ft planned. Takanock develops the land and intends to sell to an as-yet-unnamed operator. Construction reported as potentially starting in late 2027 and concluding around 2030.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-06-22 · reported proposed
Developer Takanock proposing a 180MW, 87-acre campus on land already zoned industrial, so data center use is by-right; additional permitting targeted for Q3 2027 with construction beginning the same quarter.
Sources and attribution
- 87-acre 'Project Tallmadge' to be built in Strasburg, Virginia · Data Center Dynamics (via Internet Archive)
- Strasburg data center proposal prompts questions on water use, hydrogen, oversight · The Northern Virginia Daily
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID takanock-project-tallmadge-strasburg-va. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.