Facility snapshot
- Operator as published
- Takanock, LLC
- Address and locality
- Maricopa County · Arizona
- Lifecycle status
- reported permitted
- Facility type
- data center
- Reported capacity
- Planned: 700 MW (source-reported; boundary not independently verified)
- Source freshness
- 10 September 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001424
What the source record says
Unincorporated Maricopa County near Surprise, AZ, north of Luke AFB. Construction targeted Q3 2026, first building online 2028. Coordinates are approximate. Coordinates corrected 2026-08-31 to the filed parcel (501-43-016A) in the southwest quarter of Section 28, Township 3 North, Range 1 West. The previously stored point fell roughly 8.2 miles NNW, in a different township. The 160-acre parcel holds the turbine yard, the data center buildings and the APS substation together, so a single approximate point represents the whole campus.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
No status history was supplied in this edition.
Sources and attribution
- Maricopa County supervisors approve controversial data center · ABC15
- Project Baccara - official project site · Takanock, LLC
- Arizona Corporation Commission February 4, 2026 Open Meeting Highlights — Certificate of Environmental Compatibility for Project Baccara · Arizona Corporation Commission
- Maricopa County Planning and Zoning Hearing Agenda, May 6, 2026 — case MCP250007, Project Baccara Military Compatibility Permit · Maricopa County
- 2 Data Center Projects Advancing in Metro Phoenix · AZBEX
- Certificate of Environmental Compatibility application, Baccara Power LLC (ACC docket L-21369A-25-0222-00253) — APS-owned substation interconnecting at 230 kV; 'closed loop chiller system which, once filled, will reuse water without the need for refilling'; '~100 permanent well-paying jobs'
- Maricopa County Air Quality Department, Notice of Public Hearing and Public Comment, Proposed Permit No. P0013417, Takanock Baccara LLC — facility address "NW Corner W Olive Ave & N 143rd Ave, Waddell, AZ 85355"
- Massive data center approved near Luke Air Force Base despite opposition · Arizona's Family (AZFamily)
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID takanock-project-baccara-maricopa-county-az. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.