This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Nebius Group
- Address and locality
- Vineland · Cumberland County · New Jersey
- Lifecycle status
- reported operational
- Facility type
- data center
- Reported capacity
- Operational: 100 MW; Planned: 300 MW (source-reported; boundary not independently verified)
- Source freshness
- 14 September 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001034
What the source record says
Phase-1 (~100 MW) completed summer 2025 in approximately 20 weeks from March 2025 announcement; full campus buildout targeting November 2026. Total design capacity cited as 'up to 300 MW' in Nebius press releases (sourceRef 0); DataOne CEO and local/community coverage consistently cite 350 MW; long-term campus potential described as approaching 1 GW. Coordinates are approximate (site: South Lincoln and Sheridan Avenues, East Vineland; Baxtel lists 805 Sheridan Ave). DataOne is the developer/builder — BSO's data center unit (launched 2024) backed by Ardian; CEO Charles-Antoine Beyney; this is DataOne's first US site (previously Grenoble and Lyon, France). Nebius is the ~10-year tenant; Microsoft GPU infrastructure agreement commencing late 2025 under multi-year AI infrastructure deal. Facility is 100% privately funded; DataOne declined a $6.2M city equipment loan amid community backlash. Distinct from Nebius's Independence, MO (Kansas City) site. NJDEP air permit pending as of early 2026; construction proceeded ahead of final permit issuance. DataOne stated 200+ permanent full-time jobs; construction job count not disclosed.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-03 · reported proposed
Nebius and DataOne announce phased AI data center in Vineland, NJ; 20-week first-phase build target, total ceiling 'up to 300 MW'
- 2025 · reported operational
First phase completed in approximately 20 weeks (summer 2025); Nebius committed to 100 MW installed capacity by year-end 2025; Microsoft GPU capacity deliveries begin late 2025. Full campus buildout targeting November 2026.
Sources and attribution
- Nebius accelerates US expansion, adding up to 300 MW capacity at new data center in New Jersey · Nebius
- We're introducing the 300 MW New Jersey region and expanding to Iceland · Nebius
- DataOne to build Nebius data center in New Jersey · Data Center Dynamics
- Vineland residents are protesting AI data center as concerns mount over emissions · WHYY
- A Town Hall Too Late – Vineland Data Center · Pinelands Alliance
- South Jersey's largest data center is being built in Vineland. Some residents say they've had no say in the process. · Philadelphia Inquirer
- 'Vineland data center makes case for on-site power generation during 6-hour hearing' — WHYY, 6 August 2026 · WHYY
- 'Vineland planning board approves 2nd phase of 300-megawatt data center plan' — WHYY, 18 August 2026 · WHYY
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID nebius-vineland-nj. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.