Helios (Galaxy Digital / CoreWeave)

reported operational

Galaxy Digital

Afton · Dickens County · Texas

Planned 800 MWOperational 200 MWSource updated 10 July 2026approximate location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Galaxy Digital
Address and locality
Afton · Dickens County · Texas
Lifecycle status
reported operational
Facility type
data center
Reported capacity
Operational: 200 MW; Planned: 800 MW (source-reported; boundary not independently verified)
Source freshness
10 July 2026
Location precision
approximate
Source confidence
reported
Stable directory ID
dcd-dir-000691

What the source record says

Built by Argo Blockchain as a 180 MW Bitcoin-mining facility (2022), sold to Galaxy Digital in Dec 2022 amid the crypto downturn. Galaxy has converted the site to AI/HPC hosting for CoreWeave under a 15-year lease signed March 28, 2025; ERCOT has approved 800 MW for the site (up from the original 180 MW mining build). Bitcoin mining is reported wound down (equipment removal/demolition began Q2 2025) ahead of the CoreWeave conversion — no source found describes concurrent mining and AI operation. The $1.4B figure is a project-financing debt facility (36-month term, secured by Phase I assets), not total investment or deal value; Galaxy separately committed $350M equity — investmentUsd is deliberately omitted rather than picking one of these ambiguous figures. A separate, unreconciled $460M figure appears in one lower-confidence source and is not repeated here as fact. Coordinates are approximate (single-source, not independently cross-verified — geocoding tools could not confirm the street address this pass).

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2022-05 · reported operational

    Argo Blockchain completes a 180 MW Bitcoin-mining facility ("Helios") on 160 acres in Dickens County, TX.

    Open cited source →

  2. 2022-12 · reported operational

    Argo sells Helios to Galaxy Digital for approximately $65M amid the 2022 crypto-market downturn, alongside a two-year hosting agreement.

    Open cited source →

  3. 2025-03 · reported under construction

    Galaxy signs a 15-year lease with CoreWeave to convert Helios to AI/HPC hosting (ERCOT-approved capacity expanded to 800 MW); Bitcoin-mining equipment wind-down begins.

    Open cited source →

  4. 2026 · reported operational

    Galaxy delivers Phase I (200 MW gross / 133 MW critical IT load) to CoreWeave; site begins generating lease revenue. Remaining phases (toward 800 MW) still under construction, financed by a $1.4B, 36-month debt facility (plus $350M Galaxy equity) closed August 2025.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID galaxy-helios-dickens-tx. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →