STAK Energy Campus

Alaska DNR's Preliminary Decision says STAK Energy Corporation applied for a 50-year state-land lease and that the Division proposes to issue a negotiated lease for a commercial natural-gas-powered data-center/HPC campus. The decision is a preliminary best-interest finding that proceeded to public notice; a later official notice extended comments through July 17, 2026. DNR expressly says this is one component of a broader permitting process, that the final finding, entry authorization, perfected lease, pipeline right-of-way, air, water, wetlands and other approvals are separate, and that plan updates require written approval before construction. No selected record establishes the final finding, entry authorization, executed lease, construction, energization, completion, or operation.

Status: proposed Status evidence: Alaska DNR ADL 422741 preliminary state-land decision dated 2026-05-12 Layer: verified Rights: reference_only