campus · MN · last checked 14 September 2026

Meta Rosemount Data Center

The City of Rosemount's current water-supply FAQ says the data center in Rosemount is under construction, and the city's development page crosswalks Bigfoot/Jimnist to Meta. The city's 2024 Annual Comprehensive Financial Report describes the 280-acre Meta/Jimnist project as under construction. The University of Minnesota Office of General Counsel says the 280-acre sale to Jimnist closed December 29, 2023, identifies Meta Platforms, Inc. as Jimnist's parent, and says a data center was being constructed on the property. This supports construction on the current municipal statement; it does not establish completion, energization, operation, tenant use, or continuous progress.

Status: construction Status evidence: current City of Rosemount FAQ, corroborated by city and public-university records Layer: verified Rights: reference_only