Canonical fields
- Stable ID: gotspace-groton-data-center-project-ct
- Unit: project
- Developer: Gotspace Data Partners LLC
- Operator: unknown
- Owner: unknown
- Tenant: unknown
- Capacity: Unknown (No independently supported figure)
- Capacity boundary: No selected official record states project critical-IT, utility-request, utility-service, generation, gross-facility, company-design, or measured-load MW. Agreement fee bands are hypothetical building categories, not this project's capacity.
- Location: Groton, CT
- Location precision: approximate — Bounded to candidate properties within the Town of Groton. The agreement lists six parcel/account references but permits substitutions and additions, so it does not establish a final facility footprint, street address, county field, or coordinates.
- Physical scale: The agreement identifies an approximately 64.01-acre portion of one listed 0 Paulson Road account. This is one candidate parcel portion, not total project acreage, acquired land, a final site, floor area, building count, or capacity.
What remains unknown
- current agreement status and any termination/default/assignment notice
- DECD agreement or certificate and power-purchase agreement
- Planning and Zoning site-plan approval or building permit
- final site, address, county field and coordinates
- owner, operator, tenant and capacity
Sources
-
Town of Groton — Groton Data Center Host Municipality Fee Agreement →Gov. record
Exact location Heading and body stating that the Town entered a host-municipality fee agreement for potential qualified data centers
What it supports Dated agreement/project existence and Town-level location; not current lifecycle, permit, construction, operation, capacity, or ownership.
-
Exact location PDF p. 1 recitals; pp. 3–4 eligibility and permit conditions; pp. 7–8 term, termination and power-purchase election, notice and possible-waiver provisions
What it supports Gotspace identity and development intent; candidate parcel list; 64.01-acre portion; conditional milestone and termination boundaries. The displayed copy leaves execution day/month blank and does not establish current agreement performance.
-
Town of Groton Council item 2022-43 — Data Center Update →Gov. record
Exact location PDF p. 16, Issue/Background paragraph stating Council approval on April 6, 2021 and that the agreement allows but does not guarantee construction
What it supports Approval date and exact non-guarantee boundary; not later permitting, continued effectiveness, or construction.