campus · NE · last checked 14 September 2026

Google Papillion Data Center

Sarpy County's 2021 annual report says Google's first data center in Papillion was already operational. The City of Papillion's April 21, 2026 building-permit report describes work inside Google's existing data centers at 14865 Gold Coast Road. Four cited rows have status Finaled and an Issued Date of April 6, 2026; that date is not a finaling date. A fifth row has status Issued and an Issued Date of April 1, 2026. This supports a campus with at least one operating data-center building on the dated records; it does not establish a finaling date, that every building or phase is complete or operating, real-time uptime, occupancy, or current IT load.

Status: operating Status evidence: Sarpy County operating statement dated 2021-12-20, corroborated by the City of Papillion permit-report snapshot dated 2026-04-21 Layer: verified Rights: reference_only

Canonical fields

What remains unknown

Sources