project · CA · last checked 13 September 2026

Gilroy Data Center

The City of Gilroy lists project AS 20-23 as under construction and records entitlement approval on July 3, 2025, a grading and underground-utility permit on December 11, 2025, and a building permit on March 19, 2026. The city identifies Amazon Web Services as the applicant; applicant does not by itself establish developer, owner or operator.

Status: construction Layer: verified Rights: reference_only

Canonical fields

What remains unknown

Sources