operating facility · IA · last checked 13 September 2026

Osmium Data Center

Iowa DNR's September 12, 2024 notice says the application was submitted to operate an existing Computer Processing and Data Preparation and Processing Services facility. Iowa DNR issued final Title V Operating Permit 24-TV-004 on October 17, 2024 for Osmium Data Center at 5855 SW Kerry St; the permit expires October 16, 2029. This establishes an existing permit-defined facility and an unexpired air-operating permit, not current IT load, every-building operation or continuous occupancy.

Status: operating Status evidence: permit-defined existing facility Layer: verified Rights: reference_only