Facility snapshot
- Operator as published
- WhiteFiber (Bit Digital)
- Address and locality
- Madison · Rockingham County · North Carolina
- Lifecycle status
- reported operational
- Facility type
- data center
- Reported capacity
- Operational: 24 MW; Planned: 200 MW (source-reported; boundary not independently verified)
- Source freshness
- 29 August 2026
- Location precision
- exact
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001575
What the source record says
Operator is WhiteFiber (Bit Digital's AI unit); Nscale is the 40 MW anchor tenant (10-year, ~$865M total contract value = revenue, not capex — in notes). ~1M sq ft, up to 150 kW/cabinet, 99 MW secured from Duke Energy, 200 MW eventual site potential (planned figure). $150M WhiteFiber equity. Madison is in Rockingham County, NC. Coordinates are the Madison town centroid. Property acquired for $45M (2025, from Unifi); the total buildout described as 'over $1B' is conditional on reaching 200 MW -> investmentUsd omitted. ~60 permanent jobs (~$67k avg) were pledged (Rockingham County) - a commitment, with the facility still under construction -> jobs honest-zero. Cooling type not publicly disclosed -> water honest-zero.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025 · reported under construction
WhiteFiber (Bit Digital's AI unit) acquired a ~1M sq ft NC industrial property for an AI/HPC campus; Nscale signed a 10-year, 40 MW anchor colocation (~$865M TCV)
- 2026-08-15 · reported operational
WhiteFiber's Q2 2026 results report that NC-1 has moved from construction into customer deployment: initial capacity has been delivered, equipment startup and customer testing are underway, initial billing has commenced, and full contracted run-rate billing across the 40 MW of contracted IT load was expected during August 2026.
Sources and attribution
- Nscale agrees $865m deal for 40MW of space at WhiteFiber data center in North Carolina · Data Center Dynamics
- Announcing NC-1: New Flagship Data Center in North Carolina · WhiteFiber
- WhiteFiber (Bit Digital's AI unit) acquires North Carolina property; confirmed qualifying data center · Bit Digital
- Rockingham County set to welcome a $1 billion AI data center · WFDD
- WhiteFiber, Inc. Reports Second Quarter 2026 Results · WhiteFiber, Inc. via PR Newswire
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID whitefiber-nc1-madison-nc. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.