SmartTec Site 01 (Mead)

reported proposed

SmartTec by Z1Power

8460 US Highway 70 · Mead · Bryan County · Oklahoma · 73449

Planned 0.114 MWSource updated 14 September 2026approximate location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
SmartTec by Z1Power
Address and locality
8460 US Highway 70 · Mead · Bryan County · Oklahoma · 73449
Lifecycle status
reported proposed
Facility type
data center
Reported capacity
Planned: 0.114 MW (source-reported; boundary not independently verified)
Source freshness
14 September 2026
Location precision
approximate
Source confidence
reported
Stable directory ID
dcd-dir-001326

What the source record says

Very small GPU colocation site on US-70 in Bryan County: three existing buildings (A 1,500 sq ft compute, B 2,083 sq ft batteries/utilities, C 3,535 sq ft compute), ~5,035 sq ft of gross data-center area. Phase 1A is 8× HGX-class systems, 64 GPUs, ~114 kW IT load — recorded here as 0.114 MW planned. Status is 'proposed' rather than 'under_construction' because as of 2026-09-14 the operator's own schedule puts construction start ten days out. Single-source (operator self-published), so confidence is 'reported'. Coordinates are the town of Mead; the street address did not resolve in OSM.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-09-14 · reported proposed

    Land and buildings owned; construction start scheduled 24 September 2026, transformer commissioning 8 October 2026, fiber delivery October–November 2026. Operator states the campus is not yet offering commissioned capacity.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID smarttec-site-01-mead-ok. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.