Facility snapshot
- Operator as published
- Raeden (with Cal Realty / Ferragon Corp.)
- Address and locality
- 27800 W. Jefferson Avenue · Gibraltar · Wayne County · Michigan
- Lifecycle status
- reported proposed
- Facility type
- data center
- Reported capacity
- Planned: 100 MW (source-reported; boundary not independently verified)
- Source freshness
- 9 September 2026
- Location precision
- approximate
- Source confidence
- reported
- Stable directory ID
dcd-dir-001242
What the source record says
100 MW proposal on the former McLouth Steel plant site (operated from the 1950s to 1996, now a steel processing site) at 27800 W. Jefferson Ave., with an adjacent Superfund property at 28000 W. Jefferson. Status remains 'proposed', not 'cancelled': the application is blocked by the moratorium and is the subject of active litigation, not a denial. CONFIRMED ABSENCES: no acreage, investment figure, water figure, or job count is stated in either source. The '80,000 households' comparison is the source's characterisation of the 100 MW draw, not an additional measured figure. Coordinates are the US Census geocoder's match for the street address named in the source; the parcel is not confirmed.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-02 · reported proposed
Application submitted to the city; the city asked for additional detail.
- 2026-03 · reported proposed
City council passed a one-year data-center moratorium on 2026-03-09, halting consideration.
- 2026-08 · reported proposed
Developers filed suit on 2026-08-17 seeking a declaration that the moratorium is invalid and an order compelling the city to approve the plans.
Sources and attribution
- Gibraltar faces data center developer lawsuit after city passes moratorium · Planet Detroit
- How many AI data centers are planned in Michigan? We counted. · Gander Newsroom
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID raeden-gibraltar-mclouth-mi. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.