Facility snapshot
- Operator as published
- Bitfarms Ltd.
- Address and locality
- Nesquehoning · Carbon County · Pennsylvania
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 350 MW (source-reported; boundary not independently verified)
- Source freshness
- 12 September 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-001104
What the source record says
An HPC/AI data center campus in pre-construction design at the Panther Creek waste-coal power plant site in Nesquehoning, Carbon County, with T5 Data Centers providing pre-construction design, development-approval and construction guidance. This is a separate data_center record from the already-tracked Panther Creek plant / crypto-mining operation at the same site, following the same convention as the split Homer City generation and campus records. Trade reports of a 350 MW firm power contract by 2028 (scalable toward 500 MW+) and of a special exception permit from the Nesquehoning Planning Commission were not confirmed in the sources cited here, so capacityMw and a 'permitted' status are omitted.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-08-05 · reported proposed
Bitfarms announced a partnership with T5 Data Centers for pre-construction design planning and development approvals for an HPC/AI data center at the Panther Creek campus.
- 2026-08-31 · reported under construction
Bitfarms converted its Macquarie facility into $300M of project financing on October 10, 2025 and drew an additional $50M specifically to fund civil works and substation construction at Panther Creek, with groundbreaking and commencement of civil works in Q4 2025 and Phase 1 energization expected by year-end 2026. The Nesquehoning Planning Commission granted a special exception permit on February 24, 2026 for Phase 1 — four buildings totalling 315,000 sq ft on 90 acres.
Sources and attribution
- Bitfarms Announces Partnership with T5 Data Centers to Advance HPC/AI Development at Panther Creek Campus · Bitfarms Ltd.
- Bitfarms Announces Partnership To Develop A.I. Data Center At Panther Creek Waste Coal-Fired Power Plant In Carbon County · PA Environment Digest
- Bitfarms Converts Macquarie Debt Facility to $300M Project Financing and Draws Additional $50M to Accelerate HPC/AI Development at Panther Creek Campus · Bitfarms Ltd.
- Local officials greenlight Bitfarms Panther Creek AI data center · Times News Online (via Yahoo Finance)
- Public meeting to be held Thursday on data center proposal in Carbon County · WFMZ-TV 69 News
- Nesquehoning data center plans need work · Times News Online
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID panther-creek-hpc-ai-campus-nesquehoning-pa. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.