This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Nexus Data Centers
- Address and locality
- Hubbard · Hill County · Texas
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 612 MW (source-reported; boundary not independently verified)
- Source freshness
- 25 August 2026
- Location precision
- approximate
- Source confidence
- reported
- Stable directory ID
dcd-dir-001048
What the source record says
612 MW first-phase data center campus on ~2,000 acres on the outskirts of Hubbard (Hill County), between Highway 171 and County Road 3369; behind-the-meter natural gas generation. Led by CEO/managing partner Ivan Van der Walt. TCEQ air permit applications filed Dec 2025 (183046, PSDTX1700, GHGPSDTX269); ~500 MW targeted online late 2026; publicly stated eventual full-buildout target ~7.7 GW. No end-user customer publicly identified. Coordinate anchored on the city of Hubbard; exact parcel not confirmed.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-08-25 · reported under construction
Nexus reached Final Investment Decision (FID) for Phase 1 after securing financing led by Eagle Point Credit Management; the project has advanced from pre-NTP development to FID and construction continues, per Aug 19 2026 reporting.
Sources and attribution
- 600MW natural gas-powered data center campus proposed in Hubbard, Texas · Data Center Dynamics
- Nexus Data Centers — Hubbard Data Center & Power Project, Hill County TX · Nexus Data Centers
- Nexus Hubbard Campus (612 MW) listing · Data Center Map
- Nexus proposes 612MW campus (Dec 2025 TCEQ filing) · Data Center View
- TCEQ Air NSR — Nexus applied air permits 183046, PSDTX1700, GHGPSDTX269 (per Dec 2025 filing) · Texas Commission on Environmental Quality
- Lake Lander — Citizens voice concerns about Nexus data center negotiations
- Nexus Data Center Project in Hubbard, Texas Reaches FID as Construction Advances · Construction Review Online
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID nexus-hubbard-campus-hill-county-tx. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.