LightEdge Ames Edge Colocation Data Center

reported proposed

LightEdge Solutions

Aviation Way · Ames · Story County · Iowa

Planned 25 MWSource updated 21 August 2026approximate location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
LightEdge Solutions
Address and locality
Aviation Way · Ames · Story County · Iowa
Lifecycle status
reported proposed
Facility type
data center
Reported capacity
Planned: 25 MW (source-reported; boundary not independently verified)
Source freshness
21 August 2026
Location precision
approximate
Source confidence
reported
Stable directory ID
dcd-dir-000864

What the source record says

Proposed single-storey edge colocation facility on roughly 10.86 acres of Ames airport land on Aviation Way, in a Planned Industrial zone, adjacent to the Ames Regional Airport and the ISU Research Park. Phased electrical demand of 3 MW in phase one, 6 MW in phase two, and as much as 25 MW at full buildout over roughly ten years — reported locally as about a 15 percent increase in the city's total consumption. LightEdge explicitly rules out AI or hyperscale use: asked whether it would house AI servers, its proposal answers 'No. This is edge colocation.' aiClassification is therefore omitted. Reported at roughly 100,000 sq ft in local coverage, but the operator's own page does not state a square footage, so it is not recorded. Distinct site from the tracked LightEdge Altoona facility.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2026-06-23 · reported proposed

    Ames City Council first reading on the proposal to lease city airport land to LightEdge; decision point scheduled for 2026-07-28.

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID lightedge-ames-ia. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.

No reviewed match is linked.

This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.

Corrections

Report an error in this row →