Licensed lead · not independently verified · dcd-dir-000844

Joule Energy and Data Center Campus

reported under construction

Joule Capital Partners

Holden · Millard County · Utah

Planned 4,000 MWSource updated 4 September 2026exact location · reported source confidence
How to read this page

This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.

Facility snapshot

Operator as published
Joule Capital Partners
Address and locality
Holden · Millard County · Utah
Lifecycle status
reported under construction
Facility type
data center
Reported capacity
Planned: 4,000 MW (source-reported; boundary not independently verified)
Source freshness
4 September 2026
Location precision
exact
Source confidence
reported
Stable directory ID
dcd-dir-000844

What the source record says

Founders Mark McDougal and David Gray converting family 4,000-acre alfalfa farm near Holden. Described by founders as largest private project in Utah history. Partnership with Caterpillar for generator sets; MOU with EnergySolutions for nuclear feasibility study. Part of Governor Cox's Operation Gigawatt initiative. Site at 4,800+ ft elevation for cooling efficiency. Coordinates approximate for Holden, Millard County. Subsidies checked at the municipal tier (2026-09-04): no site-level subsidy. Millard County commissioners are quoted on the record stating the county "did not give either development any special treatment or incentives", and no Millard County CRA/RDA public body is registered on the Utah Public Notice Website. Utah's EDTIF programme excludes data centres and the UCA 59-12-104 sales-tax exemption is self-executing, so no site-level award document exists to find.

Capacity is not ranked or totaled here.

Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.

Status history supplied by the source

  1. 2025-08 · reported proposed

    Millard County Commission approved project; site is conversion of family alfalfa farm

  2. 2025-11 · reported under construction

    Groundbreaking ceremony held November 6, 2025 outside Holden, UT; first power delivery targeted Q4 2026

    Open cited source →

Sources and attribution

Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID joule-millard-county-ut. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.