Facility snapshot
- Operator as published
- Global AI
- Address and locality
- Windsor · Weld County · Colorado
- Lifecycle status
- reported under construction
- Facility type
- data center
- Reported capacity
- Planned: 27.5 MW (source-reported; boundary not independently verified)
- Source freshness
- 26 August 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000698
What the source record says
Global AI, a New York-based firm, bought a 438-acre former Kodak/Carestream property in unincorporated Weld County near Windsor in November 2025 and is developing a 41-acre data center on it. Phase 1 is stated at 27.5 MW with an ambition to reach 1 GW; no timeline for later phases has been shared. The company says it plans to operate the site alongside Nvidia and Humain. Coordinates are approximate (former Kodak campus, Eastman Park Drive area), not parcel-confirmed.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2026-08-07 · reported under construction
Construction under way on the former Kodak/Carestream buildings; county has repeatedly ordered work stopped pending zoning approval.
Sources and attribution
- Weld County officials have told an AI company to stop construction on a new data center. Three times. (read via Internet Archive) · Colorado Public Radio
- AI Data Center Project Information — Town of Windsor · Town of Windsor, Colorado
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID global-ai-windsor-co. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.