This is a source-attributed discovery row. It can help you find a place and its citations; it is not a DataCenterData finding that the facility is distinct or currently operating.
Facility snapshot
- Operator as published
- Agincourt Investments, LLC
- Address and locality
- Valparaiso · Porter County · Indiana
- Lifecycle status
- reported cancelled
- Facility type
- data center
- Reported capacity
- Not stated
- Source freshness
- 13 September 2026
- Location precision
- approximate
- Source confidence
- confirmed
- Stable directory ID
dcd-dir-000025
What the source record says
Four-building complex proposed on city-owned land near St. Mary Medical Center off Indiana 49. No tax abatement or economic incentive was requested. Coordinates are the St. Mary Drive medical-center address used to anchor the site in public descriptions, not a parcel-confirmed footprint.
Any MW value is reproduced as source-reported context. Its measurement boundary is not established consistently enough for comparison. Unknown is not zero.
Status history supplied by the source
- 2025-01-09 · reported proposed
Valparaiso Redevelopment Commission approved a purchase option agreement giving Agincourt exclusive rights to buy roughly 180 acres of a 238-acre city-owned parcel for just over $9 million, subject to 180 days of due diligence.
- 2025-03-11 · reported cancelled
Mayor Jon Costas announced the city would cease all efforts toward a data center on the east side; Agincourt agreed to withdraw and release its land option after resident opposition at the March 10 council meeting.
Sources and attribution
- Valparaiso, Ind., Mayor Says Data Center Dead After Outcry · Government Technology
- City of Valparaiso Statement on Data Center (March 7, 2025) · GreatNews.Life
Adapted from Compute Atlas by Edward Kubiak, edition 1.33.0, under CC BY 4.0. Upstream ID agincourt-valparaiso-porter-county-in. Filtered to data-center records in the 50 U.S. states; selected fields normalized for search and display; DataCenterData directory IDs added.
This does not mean the row is wrong. It means DataCenterData has not promoted it through the independent evidence workflow.