  "schema_version": "0.1",
  "last_reviewed": "2026-09-13",
  "coverage": "Twenty-one bounded records selected from the national draft after a second primary-source extraction. This is not a census and does not make state coverage complete.",
  "publication": {
    "kind": "projects",
    "record_key": "projects",
    "multi_state": true
  },
  "projects": [
    {
      "stable_id": "vantage-lighthouse-port-washington",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Vantage Lighthouse Campus",
      "state": "WI",
      "city": "Port Washington",
      "county": "Ozaukee",
      "developer": "Vantage Data Centers",
      "operator": null,
      "lifecycle_status": "construction",
      "status_basis": "Wisconsin DNR's project page, rechecked September 12, 2026, describes the Lighthouse campus as under construction. Its June 12 air-permit issuance concerns emergency generators and does not establish campus operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Port Washington",
        "county": "Ozaukee",
        "precision": "approximate",
        "note": "DNR facility 246185280 locates the site east of Ozaukee Trail, south of Dixie Road/County Highway P and west of I-43. No street address or parcel crosswalk is established here."
      },
      "physical_scale": "DNR describes a 672-acre construction campus. This is land area, not a building count.",
      "sources": [
        {
          "title": "Port Washington Data Center Proposal",
          "url": "https://dnr.wisconsin.gov/topic/EIA/Portwashington.html",
          "type": "state environmental project page",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Opening paragraph; Required Permits and Approvals / Air Permit Applications",
          "supports": "Campus identity, developer, city, county, construction status and land area; June 12, 2026 permit event.",
          "source_type": "government"
        },
        {
          "title": "Wisconsin DNR permit tracking: facility 246185280 Vantage WI-1",
          "url": "https://apps.dnr.wi.gov/warp_ext/AM_PermitTracking2.aspx?id=38402",
          "type": "air-permit facility record",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Facility Information; Site Description; permit rows 24618528A-F01 and 25-MIN-094",
          "supports": "Bounded site location and active emergency-generator permit records; no operating-campus finding.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel crosswalk",
        "operator",
        "critical IT capacity",
        "utility service capacity",
        "opening date",
        "relationship to Oracle E. Lake Drive tax-certification records"
      ],
      "history": [
        {
          "date": "2026-06-12",
          "summary": "DNR records issuance of construction permit 25-MIN-094 and initial operation permit 24618528A-F01 for emergency generators; campus operating status is not established."
        },
        {
          "date": "2026-09-12",
          "field": "publication",
          "summary": "Added as a bounded construction-stage campus record after a second review of the cited Wisconsin DNR sources."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "qts-eagle-mountain-campus",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "QTS Eagle Mountain Campus",
      "state": "UT",
      "city": "Eagle Mountain",
      "county": "Utah",
      "developer": "QTS",
      "operator": null,
      "lifecycle_status": "construction",
      "status_basis": "Eagle Mountain City's April 20, 2026 update documents the first building's structural topping-out on April 17 and says interior and remaining-campus construction will continue. This establishes a construction milestone, not an opening.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Eagle Mountain",
        "county": "Utah",
        "precision": "approximate",
        "note": "City updates place this campus west of Meta. The 2024 RDA packet's Sweetwater #3 plan lists the historical QTS I/II parcels in Utah County; current parcel and street-address reconciliation remains open."
      },
      "physical_scale": "The April 2026 city update describes five planned first-phase buildings on approximately 193 acres; it does not establish five operating buildings.",
      "sources": [
        {
          "title": "Eagle Mountain City Celebrates Major Milestone with QTS Topping Out Ceremony",
          "url": "https://eaglemountain.gov/eagle-mountain-city-celebrates-major-milestone-with-qts-topping-out-ceremony/",
          "type": "municipal construction update",
          "published": "2026-04-20",
          "retrieved": "2026-09-12",
          "locator": "Article body, opening two paragraphs and final paragraph",
          "supports": "April 17 structural milestone, continuing construction and planned first-phase scale.",
          "source_type": "government"
        },
        {
          "title": "Construction restarts on QTS Data Center in Eagle Mountain",
          "url": "https://eaglemountain.gov/construction-restarts-on-qts-data-center-in-eagle-mountain/",
          "type": "municipal construction update",
          "published": "2025-10-29",
          "retrieved": "2026-09-12",
          "locator": "Article body, opening two paragraphs and construction-resumption paragraph",
          "supports": "QTS developer identity, campus west of Meta and resumed construction.",
          "source_type": "government"
        },
        {
          "title": "Eagle Mountain Redevelopment Agency August 20, 2024 meeting packet",
          "url": "https://www.utah.gov/pmn/files/1158232.pdf",
          "type": "municipal meeting packet containing proposed agreement and attached project-area plan",
          "published": "2024-08-15",
          "retrieved": "2026-09-12",
          "locator": "PDF p. 75 / printed p. 6, Amended Sweetwater Industrial Park CRA #3 plan, Table 1 and boundary description; packet cover posting certificate",
          "supports": "Historical QTS I/II parcel grouping, county and location context only. The packet is not proof that a proposed agreement was executed.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "current street address",
        "current parcel crosswalk",
        "operator",
        "critical IT capacity",
        "utility service capacity",
        "opening date",
        "relationship to other QTS Eagle Mountain/Fairfield and North Virtual Drive projects"
      ],
      "history": [
        {
          "date": "2025-10-29",
          "summary": "City reported that campus construction had resumed."
        },
        {
          "date": "2026-04-17",
          "summary": "City subsequently documented structural topping-out of the first building; additional construction remained."
        },
        {
          "date": "2026-09-12",
          "field": "publication",
          "summary": "Added as a bounded construction-stage campus record after a second review of the cited Eagle Mountain City sources."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "project-jupiter-santa-teresa",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Project Jupiter",
      "state": "NM",
      "city": null,
      "county": "Doña Ana",
      "developer": "STACK Infrastructure and BorderPlex Digital Assets",
      "operator": null,
      "lifecycle_status": "construction",
      "status_basis": "Doña Ana County's April 14, 2026 update describes the data-center campus as under construction in the Santa Teresa Industrial Park. No reviewed source establishes operation.",
      "capacity": {
        "value": 2462,
        "unit": "MW",
        "kind": "generation",
        "scope": "site",
        "aggregation_allowed": false,
        "note": "Requested YGI Microgrid generation in a pending air-permit application; not critical IT load, utility demand or issued capacity."
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Doña Ana",
        "precision": "approximate",
        "note": "Santa Teresa Industrial Park in unincorporated Doña Ana County; no primary-source parcel or campus coordinate established."
      },
      "physical_scale": "Four anticipated data-center facilities in Ordinance 367-2025.",
      "sources": [
        {
          "title": "Doña Ana County Ordinance No. 367-2025",
          "url": "https://www.donaana.gov/Documents/About%20Us/Economic%20Development%20Projects/Ordinance%20No.%20367-2025%20IRB%20Adoption_Executed%26Recorded.pdf",
          "type": "executed and recorded industrial-revenue-bond ordinance",
          "published": "2025-09-22",
          "retrieved": "2026-09-12",
          "locator": "Recorded p. 1, lines 5-25; Instrument 2520581",
          "supports": "Project identity, county and four anticipated facilities.",
          "source_type": "government"
        },
        {
          "title": "Doña Ana County Project Jupiter update",
          "url": "https://www.donaana.gov/news_detail_T7_R102.php",
          "type": "county project update",
          "published": "2026-04-14",
          "retrieved": "2026-09-12",
          "locator": "Opening project-description paragraph",
          "supports": "Construction status and Santa Teresa Industrial Park location.",
          "source_type": "government"
        },
        {
          "title": "NMED amended hearing notice, AQB 26-57(P), NSR 10883",
          "url": "https://www.env.nm.gov/opf/wp-content/uploads/sites/13/2026/07/2026-08-12-AQB-26-57-Amended-Notice-of-Hearing-English-filed.pdf",
          "type": "pending air-permit hearing notice",
          "published": "2026-08-12",
          "retrieved": "2026-09-12",
          "locator": "p. 1, Brief Description of Permit Application",
          "supports": "Related microgrid applicant, proposed generation capacity and location; not an issued permit.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel",
        "owner",
        "operator",
        "critical IT capacity",
        "utility service capacity",
        "issued microgrid permit"
      ],
      "history": [
        {
          "date": "2025-09-22",
          "summary": "County recorded Ordinance 367-2025."
        },
        {
          "date": "2026-04-14",
          "summary": "County described the campus as under construction."
        },
        {
          "date": "2026-08-12",
          "summary": "NMED noticed a hearing on the pending 2,462 MW generation application."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "project-mitten-saline-township",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Project Mitten",
      "state": "MI",
      "city": "Saline Township",
      "county": "Washtenaw",
      "developer": "RD Michigan Property Owner I LLC",
      "operator": null,
      "lifecycle_status": "construction",
      "status_basis": "Saline Township's March 18, 2026 update says Compute 1 pylons were finished and utility and foundation work was underway.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Saline Township",
        "county": "Washtenaw",
        "precision": "approximate",
        "note": "Approximately 575 acres on the north side of US-12."
      },
      "physical_scale": "Consent-judgment property: approximately 575 acres; site-plan narrative describes three planned compute buildings of about 550,000 square feet each.",
      "sources": [
        {
          "title": "Consent Judgment, RD Michigan Property Owner I LLC v. Saline Township",
          "url": "https://salinetownship.org/uploads/notices/SalineDataCenterConsentJudgmentFinalExecutionCopy492124804975v1.pdf",
          "type": "court consent judgment",
          "published": "2025-10-15",
          "retrieved": "2026-09-12",
          "locator": "Findings 1(a), 1(h)-1(r); sections 2, 4-5; Exhibit B",
          "supports": "Developer, location, site acreage, planned buildings and approval history.",
          "source_type": "government"
        },
        {
          "title": "Saline Township Data Center Update",
          "url": "http://salinetownship.org/data-center-update",
          "type": "township construction update",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "March 18, 2026 Advisory Committee entry and subsequent construction entries",
          "supports": "Active foundation, utility and later water, sanitary and stormwater work.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel crosswalk",
        "owner",
        "operator or tenant",
        "critical IT capacity",
        "utility service capacity",
        "opening date"
      ],
      "history": [
        {
          "date": "2025-09-10",
          "summary": "Township Board denied conditional rezoning."
        },
        {
          "date": "2025-10-15",
          "summary": "Consent judgment approved zoning and specified site work subject to other permits."
        },
        {
          "date": "2026-03-18",
          "summary": "Township documented active construction."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "project-cannoli-van-buren-township",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Project Cannoli",
      "state": "MI",
      "city": "Van Buren Township",
      "county": "Wayne",
      "developer": "PDC VBT, LLC",
      "operator": null,
      "lifecycle_status": "approved",
      "status_basis": "A May 19, 2026 development agreement records preliminary site-plan approvals and expressly says final site-plan approval had not yet been obtained.",
      "capacity": {
        "value": 1000,
        "unit": "MW",
        "kind": "utility_request",
        "scope": "campus",
        "aggregation_allowed": false,
        "note": "Maximum contract/load capacity in DTE testimony; not measured load, IT capacity or generation."
      },
      "location": {
        "address": null,
        "city": "Van Buren Township",
        "county": "Wayne",
        "precision": "approximate",
        "note": "East of Haggerty Road, north of the I-94 Service Drive, west of Hannan Road and south of I-275."
      },
      "physical_scale": "282.2 acres; agreement describes three planned data-center buildings, with Building 3 deferred to a future phase.",
      "sources": [
        {
          "title": "Van Buren Township Data Center FAQ — Project Cannoli",
          "url": "https://vbtmi.gov/departments/municipal_services/data_center_faq.php",
          "type": "township project page",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Opening description; items 16 and 25",
          "supports": "Project identity, location and source-document crosswalk.",
          "source_type": "government"
        },
        {
          "title": "Development Agreement between PDC VBT, LLC and Van Buren Township",
          "url": "https://vbtmi.gov/Document_Center/Department/Municipal%20Services/Development%20Agreement%20VBT%202026.05.20%20final.pdf",
          "type": "executed development agreement",
          "published": "2026-05-19",
          "retrieved": "2026-09-12",
          "locator": "Recitals A-F; sections 1.1-1.2, 2.1.2, 2.2 and 6.2; Exhibit A",
          "supports": "Developer, project area, planned buildings, preliminary approvals and missing final approval.",
          "source_type": "government"
        },
        {
          "title": "DTE testimony, MPSC Case U-22058",
          "url": "https://mi-psc.my.site.com/sfc/servlet.shepherd/version/download/068cs00001pUwYcAAK",
          "type": "utility-commission filing",
          "published": "2026-03-17",
          "retrieved": "2026-09-12",
          "locator": "NTF-8 to NTF-9, Q15-Q17",
          "supports": "Google customer identity in the utility contract and 1,000 MW maximum load/contract capacity; not operator status.",
          "source_type": "docket"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel",
        "owner",
        "operator",
        "final site-plan approval",
        "construction start",
        "critical IT capacity",
        "MPSC final disposition"
      ],
      "history": [
        {
          "date": "2026-02-11",
          "summary": "First preliminary site plan approved."
        },
        {
          "date": "2026-05-13",
          "summary": "Subsequent preliminary site plan approved."
        },
        {
          "date": "2026-05-19",
          "summary": "Development agreement executed; final site-plan approval remained outstanding."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "stack-svy03a-hayward",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "STACK SVY03A Data Center Campus",
      "state": "CA",
      "city": "Hayward",
      "county": "Alameda",
      "developer": "STACK Infrastructure",
      "operator": null,
      "lifecycle_status": "construction",
      "status_basis": "Hayward lists STACK SVY03A as under construction and records Planning Commission approval of SPR-23-0036 on May 22, 2025 with no appeal.",
      "capacity": {
        "value": 76.6,
        "unit": "MW",
        "kind": "generation",
        "scope": "campus",
        "aggregation_allowed": false,
        "qualifier": "up to",
        "note": "Current published emergency backup-generation capacity; not IT capacity or utility load."
      },
      "location": {
        "address": "26203 Production Avenue, Hayward, CA",
        "city": "Hayward",
        "county": "Alameda",
        "precision": "exact",
        "note": "Parcels 461-0085-016-00 and 461-0085-052-01."
      },
      "physical_scale": "11.3 acres and two planned data-center buildings.",
      "sources": [
        {
          "title": "California Energy Commission — STACK SVY03A, Docket 23-SPPE-01",
          "url": "https://www.energy.ca.gov/powerplant/backup-generating-system/stack-svy03a-data-center-campus",
          "type": "state energy project docket page",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Project summary and Project Description",
          "supports": "Project owner, address, planned buildings and backup-generation capacity.",
          "source_type": "docket"
        },
        {
          "title": "CEQAnet SCH 2025030999 — SVY03A",
          "url": "https://ceqanet.lci.ca.gov/2025030999",
          "type": "state environmental review record",
          "published": "2025-03-24",
          "retrieved": "2026-09-12",
          "locator": "Document Description and Location",
          "supports": "Applicant, city, county, acreage, parcels and earlier 67.2 MW generation figure.",
          "source_type": "government"
        },
        {
          "title": "City of Hayward Data Center Development Applications",
          "url": "https://www.hayward-ca.gov/business/for-developers/data-center-development-applications",
          "type": "municipal application and status page",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "FAQ: Are there currently data centers in Hayward? — STACK SVY03A",
          "supports": "Construction status, planning approval and current generation figure.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "operator or tenant",
        "critical IT capacity",
        "utility service capacity",
        "completion and energization dates"
      ],
      "history": [
        {
          "date": "2025-03-24",
          "summary": "CEQAnet described 67.2 MW of emergency generation."
        },
        {
          "date": "2025-05-22",
          "summary": "Planning Commission approved SPR-23-0036."
        },
        {
          "date": "2026-09-12",
          "summary": "Current CEC and city pages state 76.6 MW; the earlier 67.2 MW remains historical, not additive."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "willow-creek-ginger-east-west-des-moines",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Willow Creek / Ginger East permit-defined group",
      "state": "IA",
      "city": "West Des Moines",
      "county": "Polk",
      "operator": null,
      "lifecycle_status": "operating",
      "status_basis": "Iowa DNR issued Title V Operating Permit 24-TV-005 for an existing data-processing facility grouping two named data centers and two addresses.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false,
        "note": "Permit lists individual emergency engines; no campus generation total was reconstructed."
      },
      "location": {
        "address": "550 SE White Crane Road and 1475 SE Maffitt Lake Road",
        "city": "West Des Moines",
        "county": "Polk",
        "precision": "approximate",
        "note": "Two named sites and addresses in one air permit; not a settled physical-facility count."
      },
      "sources": [
        {
          "title": "Iowa DNR Title V Operating Permit 24-TV-005",
          "url": "https://www.iowadnr.gov/media/7168/download?inline",
          "type": "issued air operating permit",
          "published": "2024-12-09",
          "retrieved": "2026-09-12",
          "locator": "Cover; p. 4 facility description; pp. 22-31 equipment tables",
          "supports": "Names, addresses, permit identity and existing facility grouping.",
          "source_type": "permit"
        }
      ],
      "confidence": "medium",
      "missing_evidence": [
        "split into physical facilities",
        "parcel crosswalk",
        "owner",
        "explicit operator",
        "critical IT capacity",
        "utility service capacity",
        "opening dates"
      ],
      "history": [
        {
          "date": "2024-12-09",
          "summary": "Iowa DNR issued operating permit 24-TV-005."
        }
      ],
      "inventory_layer": "unresolved",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "meta-richland-parish",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Meta Richland Parish Data Center",
      "state": "LA",
      "city": null,
      "county": "Richland Parish",
      "operator": "Meta Platforms, Inc.",
      "lifecycle_status": "construction",
      "status_basis": "Entergy Louisiana's March 2026 sworn testimony says construction on Project Laidley continued to ramp up; a 2025 LPSC order identifies the project as Meta's data center developed through Laidley LLC.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false,
        "note": "Generic greater-than-1-GW and changing company compute-capacity statements are withheld from the counted field."
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Richland Parish",
        "precision": "approximate",
        "note": "Former Franklin Farm megasite between Rayville and Delhi."
      },
      "physical_scale": "Company/government announcement describes a four-million-square-foot campus on 2,250 acres.",
      "sources": [
        {
          "title": "Louisiana PSC Order No. U-37425",
          "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/ViewFile?fileId=nDWn/juc2+A%3D",
          "type": "utility commission order",
          "published": "2025-08-29",
          "retrieved": "2026-09-12",
          "locator": "Overview and Procedural History, pp. 1-2",
          "supports": "Meta/Laidley relationship, existence and parish location.",
          "source_type": "docket"
        },
        {
          "title": "Direct Testimony of Phillip R. May",
          "url": "https://lpscpubvalence.lpsc.louisiana.gov/portal/PSC/ViewFile?fileId=tDDeNhUDZ+w%3D",
          "type": "sworn utility testimony",
          "published": "2026-03",
          "retrieved": "2026-09-12",
          "locator": "Q13, testimony p. 12",
          "supports": "Construction was continuing to ramp up.",
          "source_type": "docket"
        },
        {
          "title": "Louisiana Economic Development Meta announcement",
          "url": "https://www.opportunitylouisiana.gov/news/meta-selects-northeast-louisiana-as-site-of-10-billion-artificial-intelligence-optimized-data-center-governor-jeff-landry-calls-investment-a-new-chapter-for-state",
          "type": "state economic-development announcement",
          "published": "2024-12-04",
          "retrieved": "2026-09-12",
          "locator": "Summary bullets and announcement body",
          "supports": "Campus area, site acreage and named-site location; announced figures are not completed outcomes.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel",
        "reconciled electrical or critical IT capacity",
        "completion and operating dates"
      ],
      "history": [
        {
          "date": "2024-12-04",
          "summary": "Campus announced."
        },
        {
          "date": "2025-08-29",
          "summary": "LPSC approved an associated generation/transmission settlement."
        },
        {
          "date": "2026-09-12",
          "event_month": "2026-03",
          "summary": "March 2026 utility testimony reported construction ramping; exact day was not established."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "sabey-intergate-quincy",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Intergate Quincy — Sabey Data Center Properties",
      "state": "WA",
      "city": "Quincy",
      "county": "Grant",
      "operator": "Sabey Data Center Properties",
      "lifecycle_status": "operating",
      "status_basis": "Washington Ecology's April 2026 approval order calls it an existing data center and approves an expansion.",
      "capacity": {
        "value": 248.1,
        "unit": "MW",
        "kind": "generation",
        "scope": "campus",
        "aggregation_allowed": false,
        "qualifier": "up to",
        "note": "Combined permitted emergency-generator capacity; not IT load or utility demand."
      },
      "location": {
        "address": "2200 M Street NE, Quincy, WA",
        "city": "Quincy",
        "county": "Grant",
        "precision": "exact",
        "note": null
      },
      "sources": [
        {
          "title": "Washington Ecology Approval Order 26AQ-E016 and technical support document",
          "url": "https://ecology.wa.gov/getattachment/af601a75-5bd5-410c-8a47-dcef65b517ca/20260406SabeyInterNOCTSD.pdf",
          "type": "issued air approval order",
          "published": "2026-04-06",
          "retrieved": "2026-09-12",
          "locator": "Approval letter and Project Summary, pp. 1-2",
          "supports": "Existing status, permittee, exact address and emergency-generator capacity.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "critical IT capacity",
        "utility service capacity",
        "measured load",
        "parcel"
      ],
      "history": [
        {
          "date": "2026-04-06",
          "summary": "Ecology issued Approval Order 26AQ-E016 for an expansion."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "amazon-attalia-walla-walla",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Amazon Attalia Data Center Campus",
      "state": "WA",
      "city": null,
      "county": "Walla Walla",
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Walla Walla County deemed the land-use and SEPA applications complete on August 24, 2026 and explicitly said no final decision had been made.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Walla Walla",
        "precision": "approximate",
        "note": "Parcel 310835410003; generally along Sundance Road between Dodd and Worden Roads."
      },
      "physical_scale": "134-acre application parcel with three proposed data-center buildings of about 220,000 square feet each; the separate 554-acre Port sale is not campus acreage.",
      "sources": [
        {
          "title": "Determination of Completeness — SDP26-01, SEPA26-05",
          "url": "https://www.wwcowa.gov/document_center/commdev/Projects/Amazon/SDP26-01%20SEPA26-05%20Determination%20of%20Completness%202026.08.24.pdf?t=202608241730540",
          "type": "county land-use completeness determination",
          "published": "2026-08-24",
          "retrieved": "2026-09-12",
          "locator": "pp. 1-2",
          "supports": "Applicant/property owner, project name, parcel, 134 acres, three buildings and proposed status; not approval.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "final land-use and SEPA decisions",
        "critical IT and utility capacity",
        "operator",
        "construction and operating dates"
      ],
      "history": [
        {
          "date": "2026-08-24",
          "summary": "County deemed the application complete; final decision remained pending."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "meta-prineville",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Meta Prineville Data Center",
      "state": "OR",
      "city": "Prineville",
      "county": "Crook",
      "operator": "Meta Platforms, Inc.",
      "lifecycle_status": "operating",
      "status_basis": "Business Oregon's 2019 table reports ongoing jobs at business operations, and 2023 material says Facebook facilities in Prineville were then receiving rural enterprise-zone abatements.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Prineville",
        "county": "Crook",
        "precision": "place_centroid",
        "note": null
      },
      "sources": [
        {
          "title": "Business Oregon currently tax-exempt energy projects and data centers",
          "url": "https://www.oregonlegislature.gov/committees/slb/WorkgroupDocuments/Arthur%20Fish,%20Business%20Oregon%20(project%20list%20-%209-25-19%20meeting).pdf",
          "type": "state incentive table",
          "published": "2019-09-25",
          "retrieved": "2026-09-12",
          "locator": "Currently tax-exempt table, Facebook Data Centers (Vitesse LLC) row",
          "supports": "Existence, Vitesse entity, Crook County and ongoing business operations.",
          "source_type": "government"
        },
        {
          "title": "Business Oregon Commission agenda item — data-center update",
          "url": "https://www.oregon.gov/biz/Publications/Boards/Business%20Oregon%20Commission/2023/AmazonSIPAgendaItem.pdf",
          "type": "state program record",
          "published": "2023-06-02",
          "retrieved": "2026-09-12",
          "locator": "Update on Data Centers in Oregon; LRZ program section",
          "supports": "Facebook data-center incentive facilities in Prineville; counts are incentive units, not verified buildings.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel",
        "critical IT and utility capacity",
        "verified current building count"
      ],
      "history": [
        {
          "date": "2019-09-25",
          "summary": "State record reported ongoing operations."
        },
        {
          "date": "2023-06-02",
          "summary": "State record reported active Prineville abatements."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "google-botetourt-greenfield",
      "parent_id": null,
      "record_unit": "campus",
      "current_name": "Google Data Center Campus — Botetourt Center at Greenfield",
      "state": "VA",
      "city": null,
      "county": "Botetourt",
      "developer": "Google; exact legal entity not stated",
      "operator": null,
      "lifecycle_status": "approved",
      "status_basis": "Botetourt County says grading plans and a land-disturbance permit were issued in August 2026. Actual grading or building construction was not established.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "campus",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Botetourt",
        "precision": "approximate",
        "note": "Botetourt Center at Greenfield; county reports a 312-acre purchase."
      },
      "sources": [
        {
          "title": "Botetourt County Google Data Center project page",
          "url": "https://www.botetourtva.gov/1021/Google-Data-Center",
          "type": "county project and permit-status page",
          "published": null,
          "retrieved": "2026-09-12",
          "locator": "Project Timeline; Public Engagement and Approval Timeline; Land Purchase",
          "supports": "Google identity, named-site location, 312-acre purchase, agreement approvals and issued grading/land-disturbance permit.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "exact legal entity",
        "street address",
        "parcel",
        "building count",
        "critical IT and utility capacity",
        "evidence grading began"
      ],
      "history": [
        {
          "date": "2025-06-20",
          "summary": "Economic Development Authority approved the performance agreement."
        },
        {
          "date": "2026-09-12",
          "event_month": "2026-08",
          "summary": "County says grading plans and a land-disturbance permit were issued in August 2026; exact day was not established and grading remained projected."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "edgecore-shannon-hill",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "EdgeCore Shannon Hill Data Center Project",
      "state": "VA",
      "city": null,
      "county": "Louisa",
      "developer": "EdgeCore Digital Infrastructure",
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Louisa County's June 24, 2025 release documents the sale of the 697-acre Shannon Hill Regional Business Park to EdgeCore for data-center development. No reviewed record establishes construction or operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Louisa",
        "precision": "approximate",
        "note": "Shannon Hill Regional Business Park off I-64; not a parcel or building coordinate."
      },
      "physical_scale": "The county identifies a 697-acre park sale. This is land area, not a building count or operating footprint.",
      "sources": [
        {
          "title": "Louisa County Sale of Shannon Hill Regional Business Park",
          "url": "https://www.louisacounty.gov/CivicAlerts.aspx?AID=470",
          "type": "county property-sale announcement",
          "published": "2025-06-24",
          "retrieved": "2026-09-13",
          "locator": "Press Release, paragraphs 1 and 4-6",
          "supports": "EdgeCore buyer/developer identity, 697-acre park, data-center development purpose and location off I-64. Water-performance statements are not adopted as independent findings.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel crosswalk",
        "operator",
        "critical IT and utility capacity",
        "building count",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded proposed-stage project after independent review of the cited Louisa County record."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "solis-arx-fluidstack-progress-park",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Solis Arx / Fluidstack Progress Park Project",
      "state": "VA",
      "city": null,
      "county": "Wythe",
      "developer": "Solis Arx; acquired by Fluidstack according to Wythe County",
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Wythe County describes a 99-acre AI-computing campus announced December 5, 2025 and a June 9, 2026 Fluidstack presentation about its acquisition of Solis Arx. No reviewed record establishes construction or operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Wythe",
        "precision": "approximate",
        "note": "A 99-acre tract in Progress Park; no street address or parcel crosswalk established."
      },
      "physical_scale": "County project page describes a 99-acre tract. It does not establish a completed building count.",
      "sources": [
        {
          "title": "Solis Arx/Fluidstack — Progress Park project page",
          "url": "https://www.wytheco.org/418/Solis-Arx",
          "type": "county project page",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Opening project description; About the Project; June 9, 2026 acquisition note",
          "supports": "Project name, Solis Arx developer role, Fluidstack acquisition statement, Wythe County location, 99-acre tract and proposed multi-phase scope.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel crosswalk",
        "operator",
        "critical IT and utility capacity",
        "construction evidence",
        "opening date"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded proposed-stage project after independent review of the cited Wythe County record."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "pairmont-data-center-campus",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Pairmont Data Center Campus",
      "state": "VA",
      "city": null,
      "county": "Spotsylvania",
      "developer": null,
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Spotsylvania County's March 25, 2026 status report names Eagle Rock Partners LLC as the applicant for rezoning case R25-0014 and lists the case as under review. Applicant identity does not by itself establish the developer or owner, and proposed acreage and floor area are not existing buildings.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Spotsylvania",
        "precision": "approximate",
        "note": "Parcels 51-A-29 and 51-A-30; access proposed through Caroline County."
      },
      "physical_scale": "County status report describes a proposal for approximately 900,000 square feet on approximately 99 acres.",
      "sources": [
        {
          "title": "Spotsylvania County Planning Department March 2026 status report",
          "url": "https://www.spotsylvania.va.us/DocumentCenter/View/40486/BOS-Memo-Planning-Dept-Monthly-and-Project-Summary-Reports-March-2026",
          "type": "county planning status report",
          "published": "2026-03-25",
          "retrieved": "2026-09-13",
          "locator": "PDF p. 4, case R25-0014",
          "supports": "Applicant, project name, parcel IDs, approximately 99-acre rezoning area, proposed 900,000 square feet and under-review status as of March 25, 2026.",
          "source_type": "government"
        },
        {
          "title": "R25-0014 Pairmont Data Center Campus case page",
          "url": "https://www.spotsylvania.va.us/3137/R25-0014-Pairmont-Data-Center-Campus",
          "type": "county planning case page",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Case heading and third-submission document list",
          "supports": "Current county case identity and continuing document docket.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "coordinates",
        "developer or owner",
        "operator",
        "critical IT and utility capacity",
        "approval outcome",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded under-review project after independent review of Spotsylvania County case records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "massaponax-tech-campus",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Massaponax Tech Campus",
      "state": "VA",
      "city": null,
      "county": "Spotsylvania",
      "developer": null,
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Spotsylvania County's March 25, 2026 status report names Lavue Lane Owner LLC as the applicant for rezoning case R25-0004 and lists the case as under review. Applicant identity does not by itself establish the developer or owner, and proposed buildout is not an operating or construction finding.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": null,
        "county": "Spotsylvania",
        "precision": "approximate",
        "note": "Twelve county parcel IDs around Massaponax Church Road, Summit Crossing Road and Mills Drive are listed in the cited status report."
      },
      "physical_scale": "County status report describes a proposal for approximately 6 million square feet of data-center buildings on approximately 588 acres.",
      "sources": [
        {
          "title": "Spotsylvania County Planning Department March 2026 status report",
          "url": "https://www.spotsylvania.va.us/DocumentCenter/View/40486/BOS-Memo-Planning-Dept-Monthly-and-Project-Summary-Reports-March-2026",
          "type": "county planning status report",
          "published": "2026-03-25",
          "retrieved": "2026-09-13",
          "locator": "PDF p. 3, case R25-0004",
          "supports": "Applicant, project name, listed parcels, approximately 588-acre rezoning area, proposed 6 million square feet and under-review status as of March 25, 2026.",
          "source_type": "government"
        },
        {
          "title": "R25-0004 Massaponax Tech Campus case page",
          "url": "https://www.spotsylvania.va.us/3138/R25-0004-Massaponax-Tech-Campus",
          "type": "county planning case page",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Case heading and fourth-submission document list",
          "supports": "Current county case identity and continuing document docket.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "coordinates",
        "developer or owner",
        "operator",
        "critical IT and utility capacity",
        "approval outcome",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded under-review project after independent review of Spotsylvania County case records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "thornburg-industrial-park-2",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Thornburg Industrial Park 2",
      "state": "VA",
      "city": null,
      "county": "Spotsylvania",
      "developer": null,
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "Spotsylvania County's March 25, 2026 status report names South Roxbury Mill LLC as the applicant for case R25-0011 and lists the case as under review. Applicant identity does not by itself establish the developer or owner. The record distinguishes a 49-acre rezoning from a proffer amendment affecting 124 acres.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": "0 S Roxbury Mill Rd",
        "city": null,
        "county": "Spotsylvania",
        "precision": "approximate",
        "note": "Parcels 63-5-C1 and 63-5-C; the address is the county case's zero-address label, not an occupied street address."
      },
      "physical_scale": "A 49-acre rezoning plus a proffer amendment affecting 124 acres. The 124 acres are not presented as a campus footprint.",
      "sources": [
        {
          "title": "Spotsylvania County Planning Department March 2026 status report",
          "url": "https://www.spotsylvania.va.us/DocumentCenter/View/40486/BOS-Memo-Planning-Dept-Monthly-and-Project-Summary-Reports-March-2026",
          "type": "county planning status report",
          "published": "2026-03-25",
          "retrieved": "2026-09-13",
          "locator": "PDF p. 4, case R25-0011",
          "supports": "Applicant, project name, parcel IDs, 49-acre rezoning, separate 124-acre proffer-amendment scope and under-review status as of March 25, 2026.",
          "source_type": "government"
        },
        {
          "title": "Spotsylvania County rezoning cases index",
          "url": "https://www.spotsylvania.va.us/799/Rezoning-Cases",
          "type": "county planning case index",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Active rezoning cases, R25-0011",
          "supports": "Current case identity in the county's active-case index.",
          "source_type": "government"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "occupied street address",
        "coordinates",
        "developer or owner",
        "operator",
        "critical IT and utility capacity",
        "approval outcome",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded under-review project after independent review of Spotsylvania County case records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "mineral-gap-data-center",
      "parent_id": null,
      "record_unit": "operating_facility",
      "current_name": "Mineral Gap Data Center",
      "state": "VA",
      "city": "Wise",
      "county": "Wise",
      "developer": null,
      "operator": null,
      "lifecycle_status": "operating",
      "status_basis": "Wise County Economic Development says Mineral Gap was established in 2017 and serves government and private clients at Lonesome Pine Business & Technology Park. The county page supports operation but does not identify the current operator.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "building",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Wise",
        "county": "Wise",
        "precision": "approximate",
        "note": "Lonesome Pine Business & Technology Park; no street address or parcel crosswalk established."
      },
      "sources": [
        {
          "title": "Data Centers — Wise County Economic Development",
          "url": "https://elevatewisecounty.com/top-industries/data-centers/",
          "type": "county economic-development page",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Mineral Gap: A Proven Model",
          "supports": "Facility name, Lonesome Pine park location, 2017 establishment and current operating description. The 3.6 MW solar array is generation, not facility IT capacity.",
          "source_type": "government"
        }
      ],
      "confidence": "medium",
      "missing_evidence": [
        "current operator",
        "street address",
        "parcel crosswalk",
        "critical IT and utility capacity",
        "current building scale"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded operating-facility record after independent review of the cited Wise County source."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "goodnight-data-center",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Goodnight Data Center",
      "state": "TX",
      "city": "Claude",
      "county": "Armstrong",
      "developer": null,
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "TCEQ names Crusoe Energy Systems LLC as the applicant for pending air-permit application 182880. The index records January 30, 2026 as the received date and links an administratively complete application; it does not establish a publication or completion date, approval, construction or operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": null,
        "city": "Claude",
        "county": "Armstrong",
        "precision": "approximate",
        "lat": 35.01752,
        "lon": -101.31175,
        "note": "TCEQ's stated point for proposed electricity generation; not a parcel survey or building centroid."
      },
      "sources": [
        {
          "title": "TCEQ Plain Language Summary — permit 182880",
          "url": "https://www.tceq.texas.gov/downloads/permitting/air/bilingual/pending-permit-notices/182880-pls-english.pdf",
          "type": "pending air-permit filing",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "PDF p. 1, lines naming applicant, facility, coordinates and proposed equipment",
          "supports": "Crusoe applicant identity, Goodnight facility name, Claude and Armstrong County location, coordinates and proposed power-generation equipment for data-center buildings. Applicant identity does not establish the developer, owner or operator.",
          "source_type": "permit"
        },
        {
          "title": "TCEQ Pending Applications: New Source Review Permits",
          "url": "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/nsr-pending-permits.html",
          "type": "state pending-permit index",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Crusoe Energy Systems LLC — Goodnight Data Center — permits 182880, GHGPSDTX268 and PSDTX1698",
          "supports": "Pending application identity, January 30, 2026 received date and link to the administratively complete application. The index does not give a publication or completion date.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "street address",
        "parcel",
        "developer or owner crosswalk",
        "operator or tenant",
        "critical IT and utility capacity",
        "generation capacity",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a permit-defined proposed project after independent review of current TCEQ records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "nexus-data-center-hubbard",
      "parent_id": null,
      "record_unit": "project",
      "current_name": "Nexus Data Center Hubbard",
      "state": "TX",
      "city": "Hubbard",
      "county": "Hill",
      "developer": null,
      "operator": null,
      "lifecycle_status": "proposed",
      "status_basis": "TCEQ names Nexus Hubbard Power, LLC as the applicant for pending applications 183046, GHGPSDTX269 and PSDTX1700. The index records February 17, 2026 as the received date and links an administratively complete application; it does not establish a publication or completion date, approval, construction or operation.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "site",
        "aggregation_allowed": false
      },
      "location": {
        "address": "880 State Highway 171",
        "city": "Hubbard",
        "county": "Hill",
        "precision": "exact",
        "note": "Address printed in the TCEQ plain-language summary; no parcel crosswalk established."
      },
      "sources": [
        {
          "title": "TCEQ Plain Language Summary — permits 183046, GHGPSDTX269 and PSDTX1700",
          "url": "https://www.tceq.texas.gov/downloads/permitting/air/bilingual/pending-permit-notices/183046-pls-english.pdf",
          "type": "pending air-permit filing",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "PDF p. 1, lines naming applicant, facility, address and proposed power-generation purpose",
          "supports": "Nexus Hubbard Power applicant identity, Nexus Data Center Hubbard name and Hubbard address. Applicant identity does not establish the developer, owner or operator. The filing concerns generation supporting the data center, not critical IT load or measured demand.",
          "source_type": "permit"
        },
        {
          "title": "TCEQ Pending Applications: New Source Review Permits",
          "url": "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/nsr-pending-permits.html",
          "type": "state pending-permit index",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Nexus Hubbard Power, LLC — Nexus Data Center Hubbard — permits 183046, GHGPSDTX269 and PSDTX1700",
          "supports": "Pending application identity, February 17, 2026 received date and link to the administratively complete application. The index does not give a publication or completion date.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "parcel",
        "coordinates",
        "developer, owner, operator or tenant",
        "critical IT and utility capacity",
        "generation capacity",
        "construction evidence"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a permit-defined proposed project after independent review of current TCEQ records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    },
    {
      "stable_id": "adc-plano",
      "parent_id": null,
      "record_unit": "operating_facility",
      "current_name": "ADC Plano",
      "state": "TX",
      "city": "Plano",
      "county": "Collin",
      "developer": null,
      "operator": null,
      "lifecycle_status": "operating",
      "status_basis": "TCEQ's pending renewal summary names Aligned Data Centers REIT LLC as the applicant for ADC Plano and says the application would authorize continued operation of 20 diesel generators and five tanks. The index records March 30, 2026 as the received date and does not establish a publication or completion date. This supports operation of the permitted facility equipment, not the applicant's current operator role or an IT-capacity figure.",
      "capacity": {
        "value": null,
        "unit": "MW",
        "kind": "unknown",
        "scope": "building",
        "aggregation_allowed": false
      },
      "location": {
        "address": "2800 Summit Avenue",
        "city": "Plano",
        "county": "Collin",
        "precision": "exact",
        "note": "Address printed in the TCEQ renewal summary; building-to-campus relationship remains unresolved."
      },
      "sources": [
        {
          "title": "TCEQ Plain Language Summary — renewal permit 131651",
          "url": "https://www.tceq.texas.gov/downloads/permitting/air/bilingual/pending-permit-notices/131651-pls-english.pdf",
          "type": "air-permit renewal filing",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "PDF p. 1, renewal summary and continued-operation statement",
          "supports": "Aligned applicant identity, ADC Plano facility name, address, county and continued operation of permitted backup equipment. Applicant identity does not establish the current operator, and generator count is not IT capacity.",
          "source_type": "permit"
        },
        {
          "title": "TCEQ Pending Applications: New Source Review Permits",
          "url": "https://www.tceq.texas.gov/assets/public/permitting/air/reports/applications/nsr-pending-permits.html",
          "type": "state pending-permit index",
          "published": null,
          "retrieved": "2026-09-13",
          "locator": "Aligned Data Centers REIT LLC — ADC Plano — permit 131651",
          "supports": "March 30, 2026 received date and link to the technically complete renewal application. The index does not give a publication or completion date.",
          "source_type": "permit"
        }
      ],
      "confidence": "high",
      "missing_evidence": [
        "parcel",
        "coordinates",
        "building-to-campus crosswalk",
        "current operator",
        "critical IT and utility capacity"
      ],
      "history": [
        {
          "date": "2026-09-13",
          "field": "publication",
          "summary": "Added as a bounded operating-facility record after independent review of current TCEQ records."
        }
      ],
      "inventory_layer": "verified",
      "rights_class": "reference_only",
      "generate_page": true
    }
  ]
}